2500 N BEACHWOOD DR 90068
Certificate Information: 2500 N BEACHWOOD DR 90068
- Application / Permit
- 20016-10000-19211
- Plan Check / Job No.
- B20LA14223
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: By adding 2 SSCC at the south elevation
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofC Issued on 11/18/2022
Permit Application Status History
| Submitted | 8/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | JESSE VIDUYA |
| Corrections Issued | 9/2/2020 | JESSE VIDUYA |
| Quality Review Completed | 9/3/2020 | HANS SANTIAGO |
| Plan Check Approved | 11/9/2020 | JESSE VIDUYA |
| Issued | 7/14/2022 | APPLICANT |
| OK for CofC | 11/16/2022 | DARRYL ARNOLD |
| CofC Issued | 11/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 10/16/2020 | ARMEN SARKISIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | ROSA SILVA |
| Tenant Habitability Plan | Cleared | 7/12/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2022 | Approved | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 8/19/2022 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 8/19/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 8/19/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 8/22/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 9/13/2022 | Conditional Approval | BRUCE CAMPBELL |
| Structural Steel Frame | 9/14/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 9/14/2022 | Approved | BRUCE CAMPBELL |
| Deputy Wood Construction | 9/20/2022 | Conditional Approval | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 9/20/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 10/4/2022 | Approved | JONATHAN QUACH |
| Final | 11/10/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Final | 11/16/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 11/16/2022 | Approved | DARRYL ARNOLD |