8122 N PASO ROBLES AVE 91406
Certificate Information: 8122 N PASO ROBLES AVE 91406
- Application / Permit
- 20016-10000-19148
- Plan Check / Job No.
- B20LA14181
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert existing detached Garage to ADU. Garage size 18'x20'
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- CofO Issued on 12/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 9/3/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/13/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 10/16/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 11/2/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/8/2021 | ARSALAN SHABESTARI |
| Issued | 3/12/2021 | APPLICANT |
| CofO in Progress | 7/20/2021 | JACK KARGODORIAN |
| CofO Issued | 12/11/2021 | MICHAEL SMITH |
| Permit Finaled | 12/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/14/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 3/3/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/3/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Build Method Construction Inc; Lic. No.: 1059684-B | 12117 VALLEYHEART DRIVE SUITE 305 STUDIO CITY, CA 91604 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 3/25/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 3/25/2021 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 3/31/2021 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 3/31/2021 | Partial Approval | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 4/8/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 4/8/2021 | Approved | ARTHUR SARGSYAN |
| Final | 6/23/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/23/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 6/23/2021 | Approved | JACK KARGODORIAN |
| Final | 7/1/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2021 | SGSOV Approved | JACK KARGODORIAN |
| Final | 7/20/2021 | OK to Issue CofO | JACK KARGODORIAN |