2918 S BEVERLY DR 90034

Certificate Information: 2918 S BEVERLY DR 90034

Application / Permit
20016-10000-19144
Plan Check / Job No.
B20LA14179
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Convert existing garage to detached ADU per state law GCS 6585.2.2(e)(1)(A). Fire sprinkler is provided throughout the building.
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
CofO Issued on 5/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 HELEN NGUYEN
Corrections Issued 9/3/2020 HELEN NGUYEN
Quality Review Completed 9/13/2020 PRANITA SHAH
Applicant returned to address corrections 10/7/2020 HELEN NGUYEN
Applicant returned to address corrections 10/22/2020 HELEN NGUYEN
Applicant returned to address corrections 11/30/2020 HELEN NGUYEN
Applicant returned to address corrections 12/10/2020 HELEN NGUYEN
Plan Check Approved 12/15/2020 HELEN NGUYEN
Issued 4/16/2021 APPLICANT
CofO in Progress 5/12/2023 CLAYTON GRAHAM
Permit Finaled 5/20/2023 DANIEL ORRANTE
CofO Issued 5/20/2023 DANIEL ORRANTE
Permit Finaled 5/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/22/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 9/22/2020 DINAH GARIN
Sewer availability Cleared 9/22/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/23/2020 DINAH GARIN
Specific Plan Cleared 9/23/2020 DYLAN SITTIG
Grading Pre-Inspection Cleared 9/28/2020 KIRK LINKLATER

Contact Information

Contractor Kor Design Build; Lic. No.: 1026877-B 4150 MAMMOTH AVE      SHERMAN OAKS, CA 91423
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 708 SOUTH REDONDO AVE      MANHATTAN BEACH, CA 90266

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/21/2021 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 7/26/2021 Corrections Issued KEVIN SARGSYAN
Sewer 7/26/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/27/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/27/2021 Approved JAVIER RAMOS JR
Underground Mechanical 9/27/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 10/26/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 10/26/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 11/12/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 11/12/2021 Approved KEVIN SARGSYAN
HVAC-Rough 11/12/2021 Corrections Issued KEVIN SARGSYAN
Special/Order Compliance 11/12/2021 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 11/18/2021 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 11/18/2021 Approved KEVIN SARGSYAN
HVAC-Rough 11/18/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/18/2021 Partial Approval KEVIN SARGSYAN
Drywall Nailing 12/2/2021 Partial Inspection KRISTEN CAUSEY
Green Building Rough 12/2/2021 Partial Inspection KRISTEN CAUSEY
Shower Pan 12/7/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/14/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 9/13/2022 Corrections Issued ANDREW NAVE
HVAC-Final 9/15/2022 Approved JOHN KIDWELL
ELECTRICAL-Final 9/16/2022 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 9/20/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 2/13/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/8/2023 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 3/13/2023 Approved ASHLEY THOMPSON
Drywall Nailing 3/13/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/13/2023 Approved ASHLEY THOMPSON
Final 3/13/2023 Corrections Issued ASHLEY THOMPSON
Green Building Final 3/13/2023 Corrections Issued ASHLEY THOMPSON
Green Building Rough 3/13/2023 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready ASHLEY THOMPSON
Smoke Detectors 3/13/2023 Approved ASHLEY THOMPSON
Final 4/11/2023 Corrections Issued ASHLEY THOMPSON
Green Building Final 4/11/2023 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Not Required ASHLEY THOMPSON
Final 5/11/2023 OK to Issue CofO CLAYTON GRAHAM