2401 N NOTTINGHAM AVE 90027
Certificate Information: 2401 N NOTTINGHAM AVE 90027
- Application / Permit
- 20016-10000-19105
- Plan Check / Job No.
- B20LA14148
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL FOR (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/28/2021
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | DANIEL YIP |
| Corrections Issued | 9/3/2020 | DANIEL YIP |
| Quality Review Completed | 9/24/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| Application Withdrawn | 10/20/2020 | ALLEN MANALANSAN |
| Plan Check Approved | 10/20/2020 | DANIEL YIP |
| Issued | 10/20/2020 | APPLICANT |
| Permit Finaled | 4/28/2021 | BRIAN SULLIVAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | M G Partners Inc; Lic. No.: 886387-B | 761 E DAILY DR #140 CAMARILLO, CA 93010 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 10/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 10/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 11/12/2020 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 11/12/2020 | Partial Approval | BRIAN SULLIVAN |
| Structural Steel Frame | 12/21/2020 | Conditional Approval | RAUL BARAJAS |
| Wood Frame | 12/21/2020 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 1/15/2021 | Conditional Approval | ROBERT CORNELL |
| Interior/Exterior Lathing | 1/27/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 4/6/2021 | Approved | BRIAN SULLIVAN |
| Final | 4/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 4/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 4/6/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/15/2021 | Partial Inspection | THOMAS LOGRASSO |
| Final | 4/19/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 4/21/2021 | Approved | BRIAN SULLIVAN |
| Final | 4/28/2021 | Permit Finaled | BRIAN SULLIVAN |