523 1/2 N CAHUENGA BLVD 90004
Certificate Information: 523 1/2 N CAHUENGA BLVD 90004
- Application / Permit
- 20016-10000-19055
- Plan Check / Job No.
- B20LA14112
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) STORAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | LAMAR DAVIS |
| Corrections Issued | 9/1/2020 | LAMAR DAVIS |
| Quality Review Completed | 9/14/2020 | TU HUA |
| Applicant returned to address corrections | 9/23/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 9/30/2020 | LAMAR DAVIS |
| Plan Check Approved | 10/9/2020 | LAMAR DAVIS |
| Issued | 10/14/2020 | APPLICANT |
| CofO in Progress | 4/21/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
| CofO Issued | 5/8/2021 | DEROLD HAUFF |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 9/24/2020 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 9/24/2020 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 9/24/2020 | SUKI GERSHENHORN |
| ZI | Cleared | 9/24/2020 | SUKI GERSHENHORN |
| Address approval | Cleared | 10/5/2020 | CELINA MORENO |
| Sewer availability | Cleared | 10/5/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | CELINA MORENO |
Contact Information
| Contractor | Distinctive Builders; Lic. No.: 683169-B | 1108 1/2 PALMS BLVD VENICE, CA 90291 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/3/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/3/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/3/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/3/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 12/3/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/3/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/9/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/9/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/10/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Insulation | 12/10/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 12/10/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/18/2020 | Approved | SCOTT FINNILA |
| Shower Pan | 12/18/2020 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 1/11/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/5/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/5/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Final | 4/5/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/5/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 4/5/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/20/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |