1572 W 182ND ST 90248

Certificate Information: 1572 W 182ND ST 90248

Application / Permit
20016-10000-19035
Plan Check / Job No.
B20LA14104
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. conversion of garage to an ADU and addition to ADU
Permit Issued
Issued on 10/28/2020
Issuing Office
Current Status
CofO Issued on 8/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 ARSALAN SHABESTARI
Corrections Issued 9/2/2020 ARSALAN SHABESTARI
Quality Review Completed 9/13/2020 PRANITA SHAH
Plan Check Approved 10/16/2020 ARSALAN SHABESTARI
Issued 10/28/2020 APPLICANT
CofO in Progress 7/14/2021 JOHN KLARIN
Permit Finaled 8/14/2021 DEROLD HAUFF
CofO Issued 8/14/2021 DEROLD HAUFF
Permit Finaled 8/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/30/2020 YEGANEH SADEGHI
Roof/Waste drainage to street Cleared 9/30/2020 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 10/1/2020 YEGANEH SADEGHI
Sewer availability Cleared 10/1/2020 YEGANEH SADEGHI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/14/2020 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 12/17/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 12/22/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/5/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 2/5/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 2/5/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 2/5/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/10/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 2/10/2021 Approved EUGENE CASSIDY
HVAC-Rough 2/10/2021 Approved EUGENE CASSIDY
Deputy Wood Construction 2/11/2021 No Access for Inspection ELMER BLAND
Insulation 2/23/2021 Approved JOHN KLARIN
Drywall Nailing 3/4/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/26/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/22/2021 Approved JOHN KLARIN
Final 4/22/2021 Corrections Issued JOHN KLARIN
Green Building Final 4/22/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/22/2021 Not Ready for Inspection JOHN KLARIN
Sewer 5/17/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 5/27/2021 Approved JOHN KLARIN
Green Building Final 6/1/2021 Approved JOHN KLARIN
ELECTRICAL-Final 6/24/2021 Corrections Issued RICHARD STEINBACH
Final 6/24/2021 Not Ready for Inspection RICHARD STEINBACH
HVAC-Final 6/24/2021 Approved RICHARD STEINBACH
PLUMBING-Final 6/24/2021 Approved RICHARD STEINBACH
Smoke Detectors 6/24/2021 Approved RICHARD STEINBACH
Final 7/2/2021 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Final 7/13/2021 Approved JOHN KLARIN
Final 7/13/2021 OK to Issue CofO JOHN KLARIN