1114-1114 1/2 E LANZIT AVE 90059

Certificate Information: 1114-1114 1/2 E LANZIT AVE 90059

Application / Permit
20016-10000-18908
Plan Check / Job No.
B20LA14025
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE AND PORTION OF (E) S.F.D TO ADU PER CA GOVT. CODE 65852.2(e )(1)(A). INTETERIOR STRUCTURAL REMODEL PER PROVIDED IN THE PLAN.
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 9/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 MAHNAZ NOURHASHEMI
Corrections Issued 9/16/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 9/29/2020 JASON HEALEY
Plan Check Approved 2/1/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 2/9/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 2/9/2022 MAHNAZ NOURHASHEMI
Issued 2/10/2022 APPLICANT
Building Plans Picked Up 2/16/2022 APPLICANT
CofO in Progress 8/14/2023 JOHN KLARIN
CofO Issued 9/27/2023 ANSON MAGLASANG
Permit Finaled 9/27/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/19/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 11/19/2021 CELINA MORENO
Sewer availability Cleared 11/19/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/30/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 3/7/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 3/9/2022 Approved JOHN KLARIN
Insulation 3/9/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 5/26/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 5/26/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/6/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 6/6/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 6/22/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/27/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 7/15/2022 No Access for Inspection JOHN KLARIN
Green Building Rough 7/15/2022 No Access for Inspection JOHN KLARIN
Drywall Nailing 7/20/2022 Corrections Issued JOHN KLARIN
Green Building Rough 7/20/2022 Approved JOHN KLARIN
Drywall Nailing 7/21/2022 Approved JOHN KLARIN
ELECTRICAL-Final 10/26/2022 Corrections Issued JOHN KLARIN
PLUMBING-Final 10/26/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/23/2022 Approved JOHN KLARIN
Final 11/23/2022 Corrections Issued JOHN KLARIN
Green Building Final 11/23/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 11/23/2022 Not Ready for Inspection JOHN KLARIN
Final 4/21/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 4/21/2023 Partial Approval JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 4/21/2023 Not Ready for Inspection JAMES CHAVEZ
Final 5/26/2023 Corrections Issued JOHN KLARIN
Green Building Final 5/26/2023 Approved JOHN KLARIN
Smoke Detectors 5/26/2023 Approved JOHN KLARIN
Final 5/31/2023 Corrections Issued JOHN KLARIN
Final 8/11/2023 OK to Issue CofO JOHN KLARIN