3018 W 39TH ST 90008

Certificate Information: 3018 W 39TH ST 90008

Application / Permit
20016-10000-18876
Plan Check / Job No.
B20LA13977
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW
Permit Issued
Issued on 11/13/2020
Issuing Office
Current Status
CofO Issued on 10/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/12/2020 SINA KHOSRAVI
Corrections Issued 8/13/2020 SINA KHOSRAVI
Applicant returned to address corrections 9/23/2020 CRISTINA SALAZAR
Plan Check Approved 10/8/2020 ADAM HEGAZI
Building Plans Picked Up 10/22/2020 APPLICANT
Issued 11/13/2020 APPLICANT
CofO in Progress 10/13/2021 HORACE FULTZ
Permit Finaled 10/16/2021 DEROLD HAUFF
CofO Issued 10/16/2021 DEROLD HAUFF
Permit Finaled 10/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/24/2020 ELENA LOPEZ
Sewer availability Cleared 9/24/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/25/2020 ELENA LOPEZ

Contact Information

Contractor Triple Aaa Builder Inc; Lic. No.: 1045940-B 1221 1/2 IROLO ST      LOS ANGELES, CA 90006

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2020 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 12/11/2020 Conditional Approval STUART CHAPMAN
Deputy Drilled-In Anchors 12/15/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 12/23/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 12/23/2020 Corrections Issued FREDDIE RIVERA
Wood Frame 12/23/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/6/2021 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 1/6/2021 Approved ROBERT VORHIS
BUILDING-Rough-Frame 1/11/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 1/11/2021 Approved FREDDIE RIVERA
Green Building Rough 1/11/2021 Approved FREDDIE RIVERA
HVAC-Rough 1/11/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/11/2021 Partial Approval FREDDIE RIVERA
HVAC-Rough 1/15/2021 Approved DAVID FEILER
Insulation 1/15/2021 Conditional Approval DAVID FEILER
PLUMBING-Rough 1/15/2021 Partial Inspection DAVID FEILER
Drywall Nailing 1/22/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/29/2021 Approved DAVID FEILER
Final 10/1/2021 OK to Issue CofO HORACE FULTZ
Green Building Final 10/1/2021 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Approved HORACE FULTZ
Smoke Detectors 10/1/2021 Approved HORACE FULTZ
Pre-Inspection 10/5/2021 Corrections Issued JOAQUIN GREENOUGH