5432 3/4 W HAROLD WAY 90027
Certificate Information: 5432 3/4 W HAROLD WAY 90027
- Application / Permit
- 20016-10000-18613
- Plan Check / Job No.
- B20LA13768
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 5 CAR GARAGE INTO TWO ADU AND ADD ROOF DECK WITH PRE-APPROVED CITY OF LOS ANGELES SPIRAL STAIR PLANS.
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 2/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | JOE VO |
| Corrections Issued | 9/8/2020 | JOE VO |
| Quality Review Completed | 9/10/2020 | MINYE PAK |
| Plan Check Approved | 9/21/2021 | JOE VO |
| Issued | 10/19/2021 | APPLICANT |
| Building Plans Picked Up | 10/22/2021 | APPLICANT |
| CofO in Progress | 2/1/2023 | JOAQUIN GREENOUGH |
| CofO Issued | 2/15/2023 | DEROLD HAUFF |
| Permit Finaled | 2/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/29/2021 | DANG NGUYEN |
| Address approval | Cleared | 2/2/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | JEANIE LAM |
| Sewer availability | Cleared | 2/2/2021 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 2/12/2021 | RICHARD BRINSON |
| Specific Plan | Cleared | 3/1/2021 | DANALYNN DOMINGUEZ |
| ZI | Cleared | 3/1/2021 | DANALYNN DOMINGUEZ |
| Hydrant and Access approval | Cleared | 3/5/2021 | MATTHEW CRAIG |
| Redevelopment Project Area | Cleared | 4/9/2021 | DAVID URITA |
| Low Impact Development | Cleared | 5/6/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | JEANIE LAM |
Contact Information
| Contractor | Salgados Construction; Lic. No.: 1045950-B | 4304 LENNOX BLVD F INGLEWOOD, CA 90304 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/9/2022 | Partial Approval | RYAN SALAZAR |
| Sewer | 6/9/2022 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/14/2022 | Partial Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/17/2022 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Partial Approval | RYAN SALAZAR |
| Gas Test | 8/17/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/17/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/17/2022 | Approved | RYAN SALAZAR |
| Wood Frame | 8/17/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/30/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/30/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/30/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/30/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 8/30/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 8/30/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 9/13/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 9/19/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 9/26/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/30/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/18/2022 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/24/2022 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/29/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/30/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 11/30/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Final | 12/29/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 12/29/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 12/29/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/17/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Final | 1/24/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Final | 1/31/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |
| Gas Test | 1/31/2023 | Approved | JOAQUIN GREENOUGH |