5432 3/4 W HAROLD WAY 90027

Certificate Information: 5432 3/4 W HAROLD WAY 90027

Application / Permit
20016-10000-18613
Plan Check / Job No.
B20LA13768
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 5 CAR GARAGE INTO TWO ADU AND ADD ROOF DECK WITH PRE-APPROVED CITY OF LOS ANGELES SPIRAL STAIR PLANS.
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 JOE VO
Corrections Issued 9/8/2020 JOE VO
Quality Review Completed 9/10/2020 MINYE PAK
Plan Check Approved 9/21/2021 JOE VO
Issued 10/19/2021 APPLICANT
Building Plans Picked Up 10/22/2021 APPLICANT
CofO in Progress 2/1/2023 JOAQUIN GREENOUGH
CofO Issued 2/15/2023 DEROLD HAUFF
Permit Finaled 2/15/2023 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 1/29/2021 DANG NGUYEN
Address approval Cleared 2/2/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/2/2021 JEANIE LAM
Sewer availability Cleared 2/2/2021 JEANIE LAM
Tenant Habitability Plan Cleared 2/12/2021 RICHARD BRINSON
Specific Plan Cleared 3/1/2021 DANALYNN DOMINGUEZ
ZI Cleared 3/1/2021 DANALYNN DOMINGUEZ
Hydrant and Access approval Cleared 3/5/2021 MATTHEW CRAIG
Redevelopment Project Area Cleared 4/9/2021 DAVID URITA
Low Impact Development Cleared 5/6/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/14/2021 JEANIE LAM

Contact Information

Contractor Salgados Construction; Lic. No.: 1045950-B 4304 LENNOX BLVD F      INGLEWOOD, CA 90304

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/9/2022 Partial Approval RYAN SALAZAR
Sewer 6/9/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 6/14/2022 Partial Inspection SABAS ALONSO
ELECTRICAL-Rough 8/17/2022 Corrections Issued RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Approval RYAN SALAZAR
Gas Test 8/17/2022 Approved RYAN SALAZAR
HVAC-Rough 8/17/2022 Approved RYAN SALAZAR
PLUMBING-Rough 8/17/2022 Approved RYAN SALAZAR
Wood Frame 8/17/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 8/30/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/30/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 8/30/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/30/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 8/30/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 8/30/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/8/2022 Approved JOAQUIN GREENOUGH
Insulation 9/13/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 9/19/2022 Approved JOAQUIN GREENOUGH
Shower Pan 9/26/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/30/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 10/18/2022 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 10/24/2022 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 11/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/29/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/30/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 11/30/2022 Partial Approval JOAQUIN GREENOUGH
Final 12/29/2022 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/29/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 12/29/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Final 1/24/2023 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved JOAQUIN GREENOUGH
Final 1/31/2023 OK to Issue CofO JOAQUIN GREENOUGH
Gas Test 1/31/2023 Approved JOAQUIN GREENOUGH