6039 E BURWOOD AVE 90042
Certificate Information: 6039 E BURWOOD AVE 90042
- Application / Permit
- 20016-10000-18598
- Plan Check / Job No.
- B20LA13739
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Conversion of (E) detached 2-car garage into an ADU in BHO. Detached ADU per state law GCS 65852.2(e)(1)(A). Fire sprinkler is provided.
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | HELEN NGUYEN |
| Corrections Issued | 8/8/2020 | HELEN NGUYEN |
| Quality Review Completed | 8/28/2020 | MINYE PAK |
| Applicant returned to address corrections | 12/9/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/15/2020 | HELEN NGUYEN |
| Plan Check Approved | 3/16/2021 | HELEN NGUYEN |
| Issued | 3/23/2021 | APPLICANT |
| CofO in Progress | 12/11/2021 | CRAIG VAUGHAN |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2020 | ELAINE LEI |
| Sewer availability | Cleared | 9/28/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | ELAINE LEI |
Contact Information
| Contractor | Secure It Construction Co; Lic. No.: 750431-B | 754 COPPERTREE CT SIMI VALLEY, CA 93065 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/2/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/8/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | COREY HUPP |
| Underground Mechanical | 6/29/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 7/8/2021 | Partial Approval | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 7/8/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 7/28/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/28/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/28/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 7/28/2021 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/28/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 8/11/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/16/2021 | Approved | CRAIG VAUGHAN |
| Final | 9/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 9/8/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 9/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/10/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/10/2021 | Approved | CRAIG VAUGHAN |
| Final | 12/10/2021 | Conditional Approval | CRAIG VAUGHAN |
| HVAC-Final | 12/10/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 12/10/2021 | Approved | CRAIG VAUGHAN |