6039 E BURWOOD AVE 90042

Certificate Information: 6039 E BURWOOD AVE 90042

Application / Permit
20016-10000-18598
Plan Check / Job No.
B20LA13739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of (E) detached 2-car garage into an ADU in BHO. Detached ADU per state law GCS 65852.2(e)(1)(A). Fire sprinkler is provided.
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 HELEN NGUYEN
Corrections Issued 8/8/2020 HELEN NGUYEN
Quality Review Completed 8/28/2020 MINYE PAK
Applicant returned to address corrections 12/9/2020 HELEN NGUYEN
Applicant returned to address corrections 12/15/2020 HELEN NGUYEN
Plan Check Approved 3/16/2021 HELEN NGUYEN
Issued 3/23/2021 APPLICANT
CofO in Progress 12/11/2021 CRAIG VAUGHAN
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/28/2020 ELAINE LEI
Sewer availability Cleared 9/28/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/6/2020 ELAINE LEI

Contact Information

Contractor Secure It Construction Co; Lic. No.: 750431-B 754 COPPERTREE CT      SIMI VALLEY, CA 93065
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/2/2021 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 6/8/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval COREY HUPP
Underground Mechanical 6/29/2021 Partial Approval COREY HUPP
BUILDING-Rough-Frame 7/8/2021 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 7/8/2021 Approved COREY HUPP
BUILDING-Rough-Frame 7/28/2021 Approved CRAIG VAUGHAN
Green Building Rough 7/28/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/28/2021 Approved CRAIG VAUGHAN
Shower Pan 7/28/2021 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/28/2021 Approved CRAIG VAUGHAN
Insulation 8/11/2021 Approved CRAIG VAUGHAN
Drywall Nailing 8/16/2021 Approved CRAIG VAUGHAN
Final 9/8/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 9/8/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/8/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/8/2021 Approved CRAIG VAUGHAN
Final 11/10/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Final 12/10/2021 Approved CRAIG VAUGHAN
Final 12/10/2021 Conditional Approval CRAIG VAUGHAN
HVAC-Final 12/10/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 12/10/2021 Approved CRAIG VAUGHAN