7813 S YORKTOWN AVE 90045

Certificate Information: 7813 S YORKTOWN AVE 90045

Application / Permit
20016-10000-18420
Plan Check / Job No.
B20LA13604
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (e)
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 LAMAR DAVIS
Corrections Issued 8/24/2020 LAMAR DAVIS
Quality Review Completed 9/1/2020 TU HUA
Applicant returned to address corrections 1/8/2021 LAMAR DAVIS
Applicant returned to address corrections 2/24/2021 LAMAR DAVIS
Applicant returned to address corrections 3/3/2021 LAMAR DAVIS
Plan Check Approved 3/16/2021 LAMAR DAVIS
Issued 3/19/2021 APPLICANT
CofO in Progress 1/28/2022 BOBBY KEY
Permit Finaled 2/1/2022 DANIEL ORRANTE
CofO Issued 2/1/2022 DANIEL ORRANTE
Permit Finaled 2/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/3/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/3/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 9/3/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/3/2020 HISASHI KOBAYAKAWA
Specific Plan Cleared 9/3/2020 PEDRO AYALA
Grading Pre-Inspection Cleared 9/18/2020 KIRK LINKLATER

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Leigh Construction; Lic. No.: 782532-B 6511 81ST      LOS ANGELES, CA 90045
Engineer Canby,, John Christopher; Lic. No.: NA21514       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/21/2021 Partial Approval BRENDAN LOONEY
Underground Mechanical 4/21/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 4/29/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 5/20/2021 Partial Inspection BRENDAN LOONEY
ELECTRICAL-Rough 5/20/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 5/20/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 5/20/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 6/14/2021 Corrections Issued RICHARD ROBLES
Gas Test 6/14/2021 Approved RICHARD ROBLES
Interior/Exterior Lathing 6/14/2021 Approved RICHARD ROBLES
PLUMBING-Rough 6/14/2021 Corrections Issued RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Approved BRENDAN LOONEY
Insulation 6/30/2021 Approved BRENDAN LOONEY
Drywall Nailing 7/9/2021 Approved BRENDAN LOONEY
Gas Test 7/9/2021 Approved BRENDAN LOONEY
Green Building Rough 7/9/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/15/2021 Approved BRENDAN LOONEY
Shower Pan 7/15/2021 Approved BRENDAN LOONEY
Gas Test 8/11/2021 Approved BRENDAN LOONEY
Underground Mechanical 8/11/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 12/15/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/15/2021 Approved ENRIQUE MIRELES
Final 12/15/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/15/2021 Approved ENRIQUE MIRELES
HVAC-Final 12/15/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 12/15/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/15/2021 Approved ENRIQUE MIRELES
Final 1/21/2022 Corrections Issued BOBBY KEY
Final 1/28/2022 OK to Issue CofO BOBBY KEY