1940 1/4-1/2 N GATES ST 90031

Certificate Information: 1940 1/4-1/2 N GATES ST 90031

Application / Permit
20016-10000-18398
Plan Check / Job No.
B20LA13585
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT TWO STORY DWELLING OVER THREE CAR GARAGE TO A DWELLING AND ACCESSORY DWELLING UNIT PER ORDINACE , LAMC 12.22 A.33 (c) and (e) **SEE COMMENTS**
Permit Issued
Issued on 12/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/4/2020 STANLEY RAAP
Corrections Issued 8/6/2020 STANLEY RAAP
Applicant returned to address corrections 12/28/2020 FERNANDO FLORES
Applicant returned to address corrections 12/31/2020 FERNANDO FLORES
Applicant returned to address corrections 4/9/2021 LUKE GONZALES
Applicant returned to address corrections 7/22/2021 LUKE GONZALES
Building Plans Picked Up 8/5/2021 APPLICANT
Plan Check Approved 12/2/2022 DANIEL SMILEY
Issued 12/28/2022 APPLICANT
CofO in Progress 5/16/2024 ALIZAH MAYAGOITIA
Permit Finaled 7/3/2024 DEROLD HAUFF
CofO Issued 7/3/2024 DEROLD HAUFF
Permit Finaled 7/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/29/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/4/2021 WALLIE JONG
Hydrant and Access approval Cleared 3/19/2021 KURT CORRAL
Tenant Habitability Plan Cleared 3/16/2022 RICHARD BRINSON
Sewer availability Cleared 9/28/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 1/9/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/30/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 9/21/2023 Approved OSVALDO PARAMO
Wood Frame 10/2/2023 Corrections Issued OSVALDO PARAMO
Green Building Rough 10/12/2023 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 10/12/2023 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 10/24/2023 Corrections Issued OSVALDO PARAMO
Green Building Rough 10/31/2023 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 12/20/2023 Approved OSVALDO PARAMO
Wood Frame 12/20/2023 Approved OSVALDO PARAMO
Drywall Nailing 1/2/2024 Approved OSVALDO PARAMO
Final 2/2/2024 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 2/2/2024 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 2/2/2024 Not Ready for Inspection OSVALDO PARAMO
Final 2/20/2024 Corrections Issued OSVALDO PARAMO
Green Building Final 2/20/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 2/20/2024 Not Ready for Inspection OSVALDO PARAMO
Final 4/10/2024 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 4/10/2024 Not Ready for Inspection OSVALDO PARAMO
Final 5/13/2024 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 5/13/2024 Approved ALIZAH MAYAGOITIA
Final 5/15/2024 OK to Issue CofO ALIZAH MAYAGOITIA