2540 S AIKEN AVE 90064
Certificate Information: 2540 S AIKEN AVE 90064
- Application / Permit
- 20016-10000-18378
- Plan Check / Job No.
- B20LA13560
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND STORY ADDITION TO (E) DETACHED GARAGE AND CONVERTION TO ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/23/2020
- Issuing Office
- Current Status
- CofO Issued on 8/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2020 | RAHEL BEYENE |
| Corrections Issued | 8/3/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/4/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 9/23/2020 | SHANGQIN XIE |
| Issued | 9/23/2020 | APPLICANT |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| CofO in Progress | 7/28/2023 | CLAYTON GRAHAM |
| Permit Finaled | 8/3/2023 | DANIEL ORRANTE |
| CofO Issued | 8/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 8/6/2020 | KENTON TRINH |
| Address approval | Cleared | 8/7/2020 | NIKTA MOUSAVI |
| Construction near power lines | Cleared | 8/10/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 8/11/2020 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 8/26/2020 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Sachi Development; Lic. No.: 821150-B | 13757 IROQUOIS PLACE CHINO, CA 91710 |
| Engineer | Santos,, Michael Fernandez; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/10/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 2/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/19/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 2/24/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 2/24/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 2/24/2021 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 7/21/2021 | Conditional Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/7/2021 | No Access for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/5/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/5/2021 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 11/5/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 11/5/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/7/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 12/7/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 12/7/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/14/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/14/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 12/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/23/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/23/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/23/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/9/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/9/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 8/9/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/2/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/2/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 9/14/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 10/4/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 10/4/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/7/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/9/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/9/2023 | Approved | CLAYTON GRAHAM |
| Final | 5/9/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 5/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 5/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 5/9/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 5/9/2023 | Approved | CLAYTON GRAHAM |
| Gas Test | 5/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 6/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Gas Test | 6/9/2023 | Approved | CLAYTON GRAHAM |
| Green Building Final | 6/9/2023 | Approved | CLAYTON GRAHAM |
| Final | 7/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 7/27/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| HVAC-Final | 7/27/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 7/27/2023 | Approved | CLAYTON GRAHAM |