4016 W 59TH PL 90043
Certificate Information: 4016 W 59TH PL 90043
- Application / Permit
- 20016-10000-18363
- Plan Check / Job No.
- B20LA13545
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE IN TO AN ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | FERNANDO FLORES |
| Corrections Issued | 8/4/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/11/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 2/6/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 2/11/2022 | SAMUEL GONZALEZ |
| Issued | 4/29/2022 | APPLICANT |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| CofO in Progress | 3/8/2024 | DAVID FEILER |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/2/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 11/16/2020 | BARTON HOLMES |
| Construction near power lines | Cleared | 4/22/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/19/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/21/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 1/25/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 3/17/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 4/10/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/10/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 4/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/18/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 5/19/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/19/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/5/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 7/19/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 7/20/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/7/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 8/10/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/2/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/2/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 2/26/2024 | OK to Issue CofO | JOSE MACIAS |
| HVAC-Final | 2/26/2024 | Approved | JOSE MACIAS |