5452 S 10TH AVE 90043

Certificate Information: 5452 S 10TH AVE 90043

Application / Permit
20016-10000-18350
Plan Check / Job No.
B20LA13535
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED GARAGE/STORAGE CONVERSION INTO ADU.
Permit Issued
Issued on 11/3/2020
Issuing Office
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2020 APPLICANT
Assigned to Plan Check Engineer 8/11/2020 RAHEL BEYENE
Corrections Issued 8/11/2020 RAHEL BEYENE
Applicant returned to address corrections 10/23/2020 CRISTINA SALAZAR
Plan Check Approved 10/29/2020 CRISTINA SALAZAR
Issued 11/3/2020 APPLICANT
Building Plans Picked Up 11/4/2020 APPLICANT
CofO in Progress 6/30/2021 FREDDIE RIVERA
No Progress 2/11/2023 RICHARD STEINBACH
CofO in Progress 2/14/2023 RONALD MYRICK
Permit Finaled 2/14/2023 RONALD MYRICK
CofO Issued 2/14/2023 RONALD MYRICK
Permit Finaled 2/14/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 9/30/2020 CECILIO NAVARRO
Sewer availability Cleared 9/30/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/1/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/12/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 1/12/2021 Partial Approval DAVID FEILER
Wood Frame 1/12/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 1/15/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 1/15/2021 Approved DAVID FEILER
PLUMBING-Rough 1/15/2021 Approved DAVID FEILER
Sewer 1/15/2021 Approved DAVID FEILER
Underground Mechanical 1/15/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 1/20/2021 Approved DAVID FEILER
Green Building Rough 1/20/2021 Approved DAVID FEILER
Insulation 1/20/2021 Approved DAVID FEILER
Interior/Exterior Lathing 1/20/2021 Partial Approval DAVID FEILER
Drywall Nailing 1/26/2021 Approved ROBERT MCDOWELL
Final 4/13/2021 Corrections Issued DAVID FEILER
Green Building Final 4/13/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 4/13/2021 Not Ready for Inspection DAVID FEILER
Final 5/4/2021 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 5/4/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 5/4/2021 Approved FREDDIE RIVERA
Smoke Detectors 5/4/2021 Approved FREDDIE RIVERA
Final 6/25/2021 Not Ready for Inspection FREDDIE RIVERA
Final 6/30/2021 OK to Issue CofO FREDDIE RIVERA