1843 S BARRY AVE 90025
Certificate Information: 1843 S BARRY AVE 90025
- Application / Permit
- 20016-10000-18199
- Plan Check / Job No.
- B20LA13422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install New Ordinary Steel Moment Frame at the tuck under parking region of an existing Condominium bldg.
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Current Status
- CofC Issued on 4/1/2021
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | HANS SANTIAGO |
| Corrections Issued | 8/18/2020 | HANS SANTIAGO |
| Quality Review Completed | 8/18/2020 | SAI KHUM |
| Applicant returned to address corrections | 9/9/2020 | HANS SANTIAGO |
| Plan Check Approved | 10/28/2020 | ANDREW SANTIAGO |
| Issued | 10/28/2020 | APPLICANT |
| OK for CofC | 3/24/2021 | GRANT WOODS |
| CofC Issued | 4/1/2021 | TED RIES |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/27/2020 | MAXFIELD VERMY |
| Tenant Habitability Plan | Cleared | 10/26/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/10/2020 | Not Ready for Inspection | JOHN DODGE |
| Pre-Inspection | 12/11/2020 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 12/30/2020 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 1/5/2021 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 1/6/2021 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 1/7/2021 | Not Ready for Inspection | JOHN DODGE |
| Structural Steel Frame | 1/7/2021 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 1/7/2021 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 1/13/2021 | Approved | JOHN DODGE |
| Structural Steel Frame | 1/20/2021 | Approved | JOHN DODGE |
| Wood Frame | 1/20/2021 | Approved | JOHN DODGE |
| Drywall Nailing | 1/26/2021 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 1/26/2021 | Approved | GRANT WOODS |
| Final | 2/2/2021 | Corrections Issued | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 2/2/2021 | Approved | GRANT WOODS |
| Final | 3/24/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/24/2021 | SGSOV Approved | GRANT WOODS |