10763 N GLENOAKS BLVD 91331
Certificate Information: 10763 N GLENOAKS BLVD 91331
- Application / Permit
- 20016-10000-18161
- Plan Check / Job No.
- B20LA13388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Coffee Shop
- Work Description
- CHANGE OF USE FROM RETAIL TO COFFEE SHOP (795 SF). STATE ENTERPRISE ZONE, NO CHANGE IN PARKING.HOURS OF OPERATION WILL BE LIMITED TO 7AM TO 11PM. SIGN, PLUMBING, ELECTRICAL, AND HVAC UNDER SEPERATE PERMIT.
- Permit Issued
- Issued on 10/6/2020
- Issuing Office
- Current Status
- CofO Issued on 1/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2020 | STANLEY RAAP |
| Corrections Issued | 8/3/2020 | STANLEY RAAP |
| Plan Check Approved | 10/2/2020 | AUNG SOE |
| Issued | 10/6/2020 | APPLICANT |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
| CofO in Progress | 1/8/2021 | ANDREW DORSO |
| Permit Finaled | 1/14/2021 | JEFFREY DURAN |
| CofO Issued | 1/14/2021 | JEFFREY DURAN |
| Permit Finaled | 1/14/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/6/2020 | RUBEN VASQUEZ |
| Comm Cor/Mini-Mall | Cleared | 8/6/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/6/2020 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/11/2020 | ADRIAN CASTRO |
| Food establishment approval | Cleared | 10/2/2020 | LACDHS APPROVED |
Contact Information
| Contractor | Cal Nari Construction Inc; Lic. No.: 984933-B | 1150 S WESTMORLAND AVE #210 LOS ANGELES, CA 90006 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Approved | ANDREW DORSO |
| Footing/Foundation/Slab | 11/4/2020 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 11/5/2020 | Approved | ANDREW DORSO |
| Drywall Nailing | 11/9/2020 | Approved | ANDREW DORSO |
| Final | 1/4/2021 | Partial Approval | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV No Gas | HAMID PISHEHVAR |
| Smoke Detectors | 1/4/2021 | Approved | HAMID PISHEHVAR |
| Wood Frame | 1/4/2021 | Approved | HAMID PISHEHVAR |
| Final | 1/8/2021 | OK to Issue CofO | ANDREW DORSO |