401 S CORONADO ST 90057
Certificate Information: 401 S CORONADO ST 90057
- Application / Permit
- 20016-10000-18157
- Plan Check / Job No.
- B20LA13385
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. 4 STEEL CANTILEVER COLUMNS AND GRADE BEAM.
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- CofC Issued on 5/5/2021
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | JESSE VIDUYA |
| Corrections Issued | 8/27/2020 | JESSE VIDUYA |
| Quality Review Completed | 8/27/2020 | HANS SANTIAGO |
| Building Plans Picked Up | 9/1/2020 | APPLICANT |
| Applicant returned to address corrections | 11/4/2020 | JESSE VIDUYA |
| Plan Check Approved | 11/17/2020 | JESSE VIDUYA |
| Issued | 12/11/2020 | APPLICANT |
| OK for CofC | 5/4/2021 | MARK FERRARI |
| CofC Issued | 5/5/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 9/10/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 9/10/2020 | MICAELA TORRES-GIL |
| Tenant Habitability Plan | Cleared | 12/7/2020 | ISMAEL HERNANDEZ |
Contact Information
| Architect | Gold,, Kerry Daniel; Lic. No.: C13781 | 638 LINDERO CYN RD # 432 OAK PARK, CA 91377 |
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 2/26/2021 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 3/1/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/1/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 3/1/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/2/2021 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 3/4/2021 | Approved | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Conditional Approval | MARK FERRARI |
| Interior/Exterior Lathing | 3/12/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/19/2021 | Approved | MARK FERRARI |
| Final | 4/28/2021 | Conditional Approval | MARK FERRARI |
| METHANE-Final | 4/28/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 4/28/2021 | Approved | MARK FERRARI |
| Final | 5/4/2021 | OK for CofC | MARK FERRARI |