2219 N HOLLY DR 90068

Certificate Information: 2219 N HOLLY DR 90068

Application / Permit
20016-10000-18150
Plan Check / Job No.
B20LA13373
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL OF SINGLE FAMILY RESIDENCE. ENCLOSURE OF THE EXISTING COVERED ENTRY PORCH, NEW SIDE ENTRY, DEMO OF EXISTING INTERIOR WALLS AND ASSOC STRUCT MODIFICATIONS. 2 BATHS AND 1 KITCHEN REMODEL. REMOVE AND REPLACE 906SQ.FT ROOF AND ITS FRAMING, WALLS AND FOOTINGS.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
Issued on 3/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/1/2020 RAHEL BEYENE
Corrections Issued 8/3/2020 RAHEL BEYENE
Applicant returned to address corrections 9/24/2020 ADAM HEGAZI
Applicant returned to address corrections 10/29/2020 RAHEL BEYENE
Applicant returned to address corrections 11/12/2020 AMIR DANAI
Plan Check Approved 11/12/2020 AMIR DANAI
No Progress 11/12/2020 AMIR DANAI
Plan Check Approved 3/11/2021 RICARDO RAMIREZ
Plan Check Approved 3/18/2021 RICARDO RAMIREZ
Issued 3/18/2021 APPLICANT
Building Plans Picked Up 3/22/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/5/2021 JEANIE LAM
Construction within easement Cleared 1/12/2021 TORI CHEN
Low Impact Development Cleared 2/19/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/23/2021 JEANIE LAM
Grading Pre-Inspection Cleared 3/11/2021 RAHEL BEYENE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2021 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/28/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 6/29/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 7/28/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 9/27/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 11/29/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 12/17/2021 Not Ready for Inspection DANIEL GONZALEZ
ELECTRICAL-Rough 12/23/2021 Approved BRIAN SULLIVAN
HVAC-Rough 12/23/2021 Approved BRIAN SULLIVAN
Green Building Rough 1/4/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 1/4/2022 Approved ADAM ESCOTO
Verify Sprinkler Sign Off 1/4/2022 Approved ADAM ESCOTO
Wood Frame 1/4/2022 Corrections Issued ADAM ESCOTO
BUILDING-Rough-Frame 1/6/2022 Approved BRIAN SULLIVAN
Green Building Rough 1/6/2022 Approved BRIAN SULLIVAN
Insulation 1/12/2022 Approved BRIAN SULLIVAN
Drywall Nailing 1/19/2022 Approved BRIAN SULLIVAN
Shower Pan 2/4/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/17/2022 Partial Approval SHAVONNE ESPINOZA