818 N HILL ST 90012
Certificate Information: 818 N HILL ST 90012
- Application / Permit
- 20016-10000-18124
- Plan Check / Job No.
- B20LA13350
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- T-MOBILE IS PROPOSING TO REMOVE AND REPLACE (6) ANTENNAS AND (6) RRU'S ON AN EXISTING WIRELESS TELECOMMUNICATIONS FACILITY. T-MOBILE SITE: LA90220A WORK PER ZA-2006-9682-CU
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/17/2021
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | RICARDO RAMIREZ |
| Corrections Issued | 8/4/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 8/11/2020 | APPLICANT |
| Plan Check Approved | 11/18/2020 | GEORGE ALVAREZ |
| Issued | 2/3/2021 | APPLICANT |
| Permit Finaled | 6/16/2021 | JONATHAN QUACH |
Permit Application Clearance Information
| Plan Approval | Cleared | 10/5/2020 | JESSE RAMOS |
| ZA Case | Cleared | 10/5/2020 | JESSE RAMOS |
| ZA Case | Cleared | 10/5/2020 | JESSE RAMOS |
| ZA Case | Cleared | 10/5/2020 | JESSE RAMOS |
| ZA Case | Cleared | 10/5/2020 | JESSE RAMOS |
| ZA Case | Cleared | 10/5/2020 | JESSE RAMOS |
| ZA Case | Cleared | 10/5/2020 | JESSE RAMOS |
| Historic Resource Verification | Cleared | 10/13/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 11/5/2020 | DAVID URITA |
| ZI | Cleared | 11/5/2020 | DAVID URITA |
Contact Information
| Contractor | Mastec Network Solutions Inc; Lic. No.: 984138-B | 1825 PONCE DE LEON BLVD #543 CORAL GABLES, FL 33134 |
| Engineer | Bronnenkant,, Adam Paul; Lic. No.: C74190 | 23650 N 84TH PL SCOTTSDALE, AZ 85255 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 4/8/2021 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 4/8/2021 | Approved | RONALD PACHECO |
| Final | 4/22/2021 | Not Ready for Inspection | RONALD PACHECO |
| Final | 5/26/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 6/15/2021 | No Access for Inspection | JONATHAN QUACH |
| Final | 6/16/2021 | Permit Finaled | JONATHAN QUACH |