23425-23427 S HALLDALE AVE 90710
Certificate Information: 23425-23427 S HALLDALE AVE 90710
- Application / Permit
- 20016-10000-18113
- Plan Check / Job No.
- B20LA13338
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED GARAGE CONVERSION INTO AN ACCESSORY DWELLING UNIT (ADU) (430 SQ FT) PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/23/2021
- Issuing Office
- Current Status
- CofO Issued on 12/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | CRISTINA SALAZAR |
| Corrections Issued | 8/4/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 8/12/2020 | APPLICANT |
| Applicant returned to address corrections | 9/10/2020 | TSE MING HUANG |
| Plan Check Approved | 11/18/2020 | CRISTINA SALAZAR |
| Issued | 12/23/2021 | APPLICANT |
| CofO in Progress | 12/6/2023 | JAMES CHAVEZ |
| Permit Finaled | 12/6/2023 | ANSON MAGLASANG |
| CofO Issued | 12/6/2023 | ANSON MAGLASANG |
| Permit Finaled | 12/6/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2020 | CHINH DINH |
| Permit | Cleared | 8/18/2020 | CHINH DINH |
| Sewer availability | Cleared | 8/18/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Domenico And Sons Inc; Lic. No.: 958606-B | 18014 SOUTH VERMONT AVE GARDENA, CA 90248 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/10/2022 | Partial Inspection | JOHN KLARIN |
| Wood Frame | 2/2/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/15/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 2/15/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/6/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 4/6/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/22/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/22/2022 | Partial Approval | EUGENE CASSIDY |
| Insulation | 8/25/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 8/25/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/4/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/5/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/5/2022 | Approved | EUGENE CASSIDY |
| Final | 7/28/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/28/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/28/2023 | Approved | EUGENE CASSIDY |
| Final | 9/29/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/29/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/4/2023 | Approved | EUGENE CASSIDY |
| Final | 10/4/2023 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 10/4/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/3/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/4/2023 | Approved | JAMES CHAVEZ |
| Final | 12/4/2023 | OK to Issue CofO | JAMES CHAVEZ |
| HVAC-Final | 12/4/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 12/4/2023 | Approved | JAMES CHAVEZ |