2518 W AVENUE 31 90065
Certificate Information: 2518 W AVENUE 31 90065
- Application / Permit
- 20016-10000-18093
- Plan Check / Job No.
- B20LA13321
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* ADDITION & CONVERSION OF (E) GARAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (e). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | LAMAR DAVIS |
| Corrections Issued | 8/25/2020 | LAMAR DAVIS |
| Quality Review Completed | 9/1/2020 | TU HUA |
| Applicant returned to address corrections | 2/3/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 2/25/2021 | LAMAR DAVIS |
| Plan Check Approved | 3/4/2021 | LAMAR DAVIS |
| Issued | 3/12/2021 | APPLICANT |
| CofO in Progress | 8/8/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
| CofO Issued | 8/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Watercourse | Cleared | 8/27/2020 | SAM NAVID |
| Address approval | Cleared | 9/2/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/2/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 9/30/2020 | PATRICK MISCHLICH |
| Supp. Use District POD/CDO/TDO | Cleared | 10/15/2020 | ADRINEH MELKONIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/14/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 7/6/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/13/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/13/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/20/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/23/2022 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 2/23/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Service/Power Release | 5/11/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 5/11/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 5/25/2022 | Approved | AMY COLIN |
| Final | 5/25/2022 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 5/25/2022 | Approved | AMY COLIN |
| Green Building Final | 5/25/2022 | Corrections Issued | AMY COLIN |
| HVAC-Final | 5/25/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 5/25/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 5/25/2022 | Approved | AMY COLIN |
| Final | 6/27/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/27/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 7/21/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 8/4/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |