2518 W AVENUE 31 90065

Certificate Information: 2518 W AVENUE 31 90065

Application / Permit
20016-10000-18093
Plan Check / Job No.
B20LA13321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* ADDITION & CONVERSION OF (E) GARAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (e). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 LAMAR DAVIS
Corrections Issued 8/25/2020 LAMAR DAVIS
Quality Review Completed 9/1/2020 TU HUA
Applicant returned to address corrections 2/3/2021 LAMAR DAVIS
Applicant returned to address corrections 2/25/2021 LAMAR DAVIS
Plan Check Approved 3/4/2021 LAMAR DAVIS
Issued 3/12/2021 APPLICANT
CofO in Progress 8/8/2022 HAMIK HARTOUNIAN
Permit Finaled 8/11/2022 DEROLD HAUFF
Permit Finaled 8/11/2022 DEROLD HAUFF
CofO Issued 8/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Watercourse Cleared 8/27/2020 SAM NAVID
Address approval Cleared 9/2/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 9/2/2020 JEANIE LAM
Sewer availability Cleared 9/2/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/24/2020 JEANIE LAM
Grading Pre-Inspection Cleared 9/30/2020 PATRICK MISCHLICH
Supp. Use District POD/CDO/TDO Cleared 10/15/2020 ADRINEH MELKONIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/14/2021 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 7/6/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/29/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/16/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/16/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 11/16/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/16/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 11/16/2021 Approved HAMIK HARTOUNIAN
Insulation 12/13/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/13/2021 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 12/20/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/23/2022 Approved HAMIK HARTOUNIAN
Shower Pan 2/23/2022 Conditional Approval HAMIK HARTOUNIAN
Service/Power Release 5/11/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Sewer 5/11/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 5/25/2022 Approved AMY COLIN
Final 5/25/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 5/25/2022 Approved AMY COLIN
Green Building Final 5/25/2022 Corrections Issued AMY COLIN
HVAC-Final 5/25/2022 Approved AMY COLIN
PLUMBING-Final 5/25/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Not Ready AMY COLIN
Smoke Detectors 5/25/2022 Approved AMY COLIN
Final 6/27/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/27/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Approved HAMIK HARTOUNIAN
Final 7/21/2022 Corrections Issued HAMIK HARTOUNIAN
Final 8/4/2022 OK to Issue CofO HAMIK HARTOUNIAN