2030 W 42ND ST 90062
Certificate Information: 2030 W 42ND ST 90062
- Application / Permit
- 20016-10000-18089
- Plan Check / Job No.
- B20LA13316
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation.
- Permit Issued
- Issued on 10/1/2020
- Issuing Office
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 8/19/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/13/2020 | PRANITA SHAH |
| Plan Check Approved | 9/29/2020 | ARSALAN SHABESTARI |
| Issued | 10/1/2020 | APPLICANT |
| CofO in Progress | 6/1/2021 | ROBERT MCDOWELL |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 8/28/2020 | CECILIO NAVARRO |
| ZI | Cleared | 9/1/2020 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/2/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | United Dwelling Construction Inc; Lic. No.: 1066382-B | 8757 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/14/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 11/9/2020 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Approved | JOHN KLARIN |
| Wood Frame | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Wood Frame | 2/10/2021 | Approved | ROBERT MCDOWELL |
| Wood Frame | 2/17/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 2/24/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Sewer | 2/26/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/14/2021 | Conditional Approval | DAVID FEILER |
| Final | 5/14/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 5/14/2021 | Approved | DAVID FEILER |
| Green Building Final | 5/14/2021 | Approved | DAVID FEILER |
| Green Building Rough | 5/14/2021 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 5/14/2021 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 5/14/2021 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 5/14/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/1/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 6/1/2021 | Approved | ROBERT MCDOWELL |
| Final | 6/1/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| HVAC-Final | 6/1/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 6/1/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 6/1/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 6/1/2021 | Approved | ROBERT MCDOWELL |