343 1/2 N AVENUE 61 90042

Certificate Information: 343 1/2 N AVENUE 61 90042

Application / Permit
20016-10000-18054
Plan Check / Job No.
B20LA13285
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING DETACHED 1-STORY REC ROOM & GARAGE INTO AN ADU
Permit Issued
Issued on 6/10/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 JOE VO
Corrections Issued 8/26/2020 JOE VO
Quality Review Completed 9/4/2020 MINYE PAK
Plan Check Approved 9/30/2020 JOE VO
Issued 6/10/2021 APPLICANT
CofO in Progress 5/10/2022 AMY COLIN
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 9/23/2020 KATIE DEBIASE
Historic monument Cleared 9/23/2020 KATIE DEBIASE
ZI Cleared 9/23/2020 KATIE DEBIASE
Address approval Cleared 9/28/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/28/2020 WALLIE JONG
Sewer availability Cleared 9/28/2020 WALLIE JONG

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/7/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 7/7/2021 Corrections Issued COREY HUPP
BUILDING-Rough-Frame 7/16/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 7/16/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 7/16/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 8/27/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 8/27/2021 Corrections Issued SCOTT FINNILA
Green Building Rough 8/27/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 8/27/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 8/27/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 11/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 11/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 11/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/2/2021 Corrections Issued COREY HUPP
ELECTRICAL-Rough 12/2/2021 Approved COREY HUPP
Green Building Rough 12/2/2021 Not Ready for Inspection COREY HUPP
HVAC-Rough 12/2/2021 Not Ready for Inspection COREY HUPP
Rough-Elec/Plmb/HVAC 12/2/2021 Approved COREY HUPP
Shower Pan 1/21/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/26/2022 Partial Inspection AMY COLIN
Final 4/26/2022 Corrections Issued AMY COLIN
Gas Test 4/26/2022 Approved AMY COLIN
Green Building Final 4/26/2022 Corrections Issued AMY COLIN
Green Building Rough 4/26/2022 Approved AMY COLIN
Smoke Detectors 4/26/2022 Approved AMY COLIN
BUILDING-Rough-Frame 5/9/2022 Approved AMY COLIN
Final 5/9/2022 Partial Inspection AMY COLIN
Green Building Final 5/9/2022 Approved AMY COLIN
ELECTRICAL-Final 5/10/2022 Approved AMY COLIN
Final 5/10/2022 OK to Issue CofO AMY COLIN
HVAC-Final 5/10/2022 Approved AMY COLIN
PLUMBING-Final 5/10/2022 Approved AMY COLIN
Service/Power Release 5/10/2022 Approved AMY COLIN