13911 W HERRON ST 91342

Certificate Information: 13911 W HERRON ST 91342

Application / Permit
20016-10000-17947
Plan Check / Job No.
B20LA13215
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 20'-0 x 19'-0" GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK PER WFPP
Permit Issued
Issued on 10/6/2022
Issuing Office
Current Status
Issued on 10/6/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/30/2020 APPLICANT
Assigned to Plan Check Engineer 8/2/2020 STANLEY RAAP
Corrections Issued 8/3/2020 STANLEY RAAP
Building Plans Picked Up 8/17/2020 APPLICANT
Applicant returned to address corrections 9/26/2022 ALFRED RAMIREZ
Plan Check Approved 10/6/2022 DANIEL ABRAMYAN
Issued 10/6/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/21/2020 GUILLERMO PETRA
Address approval Cleared 10/22/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/22/2020 GUILLERMO PETRA
Construction near power lines Cleared 7/16/2021 RIDWAN HARDY
Construction within easement Cleared 7/16/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 7/30/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2023 Not Ready for Inspection ARAM AVEDISIAN
Underground Mechanical 2/7/2023 Not Ready for Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 2/10/2023 Approved MATTHEW NELSON
Footing/Foundation/Slab 2/10/2023 Approved MATTHEW NELSON
Underground Mechanical 2/10/2023 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 3/3/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/3/2023 Approved ARAM AVEDISIAN
Wood Frame 3/3/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 3/8/2023 Approved ARAM AVEDISIAN
Green Building Rough 3/8/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/8/2023 Partial Approval ARAM AVEDISIAN
Sewer 3/8/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/13/2023 Approved ARAM AVEDISIAN
Insulation 3/13/2023 Approved ARAM AVEDISIAN
Drywall Nailing 3/22/2023 Approved ARAM AVEDISIAN
Shower Pan 3/22/2023 Approved ARAM AVEDISIAN