6028 S 7TH AVE 90043

Certificate Information: 6028 S 7TH AVE 90043

Application / Permit
20016-10000-17869
Plan Check / Job No.
B20LA13183
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU .RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
Permit Issued
Issued on 10/21/2020
Issuing Office
Current Status
CofO Issued on 8/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 ARSALAN SHABESTARI
Corrections Issued 8/17/2020 ARSALAN SHABESTARI
Quality Review Completed 9/13/2020 PRANITA SHAH
Applicant returned to address corrections 10/15/2020 ARSALAN SHABESTARI
Plan Check Approved 10/15/2020 ARSALAN SHABESTARI
Issued 10/21/2020 APPLICANT
CofO in Progress 6/30/2021 FREDDIE RIVERA
CofO Issued 8/14/2021 DEROLD HAUFF
Permit Finaled 8/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/28/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 8/28/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/1/2020 CECILIO NAVARRO
Sewer availability Cleared 9/2/2020 CECILIO NAVARRO

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2020 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 11/10/2020 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/18/2020 Approved FREDDIE RIVERA
Wood Frame 2/8/2021 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Approved FREDDIE RIVERA
Sewer 2/16/2021 Partial Approval FREDDIE RIVERA
Sewer 2/24/2021 Approved FREDDIE RIVERA
Pre-Inspection 3/4/2021 Corrections Issued FREDDIE RIVERA
Sewer 3/4/2021 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/17/2021 Approved FREDDIE RIVERA
Final 3/17/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 3/17/2021 Approved FREDDIE RIVERA
Green Building Final 3/17/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 3/17/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 3/17/2021 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 3/17/2021 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 3/17/2021 Approved FREDDIE RIVERA
Final 4/8/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Not Ready FREDDIE RIVERA
Final 6/3/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 6/3/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 6/3/2021 Approved FREDDIE RIVERA
Final 6/25/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 6/25/2021 Approved FREDDIE RIVERA
Final 6/29/2021 OK to Issue CofO FREDDIE RIVERA