268 S RAMPART BLVD 90057

Certificate Information: 268 S RAMPART BLVD 90057

Application / Permit
20016-10000-17818
Plan Check / Job No.
B20LA13150
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Coffee Shop
Work Description
INTERIOR TENANT IMPROVEMENT AND CHANGE OF USE FROM BAKERY TO BOBA COFFEE SHOP (INSTALL NEW LIGHTING, OUTLETS, EQUIPMENT) (AREA OF WORK = 560 SQ FT). REMOVE PARTIALLY (E) STOREFRONT GLAZING FOR (N) PASS THROUGH WINDOW FOR TO GO. REPLACE (E) FAN COIL UNIT ABOVE TENANT SPACE CEILING WITH NEW. REPLACE (E) AC ROOF UNIT
Permit Issued
Issued on 10/8/2020
Issuing Office
Current Status
CofO Issued on 7/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 GEORGE ALVAREZ
Corrections Issued 8/7/2020 GEORGE ALVAREZ
Plan Check Approved 9/10/2020 FERNANDO FLORES
Building Plans Picked Up 9/10/2020 APPLICANT
Issued 10/8/2020 APPLICANT
CofO in Progress 7/1/2021 KATY RAMIREZ
CofO Issued 7/2/2021 ERNESTO CORRAL
Permit Finaled 7/2/2021 ERNESTO CORRAL

Permit Application Clearance Information

ZA Case Cleared 8/19/2020 RUBEN VASQUEZ
ZA Case Cleared 8/19/2020 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 8/24/2020 JEANIE LAM
Sewer availability Cleared 8/24/2020 JEANIE LAM
Food Service Establishment Cleared 8/31/2020 KENNETH BROWNE
Food establishment approval Cleared 9/9/2020 LACDHS APPROVED

Contact Information

Contractor Golden Stone Construction; Lic. No.: 887486-B 5410 N MUSCATEL AVE      SAN GABRIEL, CA 91776

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/8/2020 Corrections Issued KATY RAMIREZ
METHANE-Rough 12/15/2020 Approved KATY RAMIREZ
Wood Frame 12/15/2020 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 12/22/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 12/22/2020 Partial Inspection KATY RAMIREZ
Wood Frame 12/22/2020 Partial Inspection KATY RAMIREZ
T-Bar Ceiling 1/26/2021 Corrections Issued KATY RAMIREZ
Final 5/5/2021 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 5/5/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 5/5/2021 Approved KATY RAMIREZ
Wood Frame 5/5/2021 Approved KATY RAMIREZ
Final 6/15/2021 Partial Inspection KATY RAMIREZ
Pre-Inspection 6/15/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV No Gas KATY RAMIREZ
Final 7/1/2021 OK to Issue CofO KATY RAMIREZ