14417 W VALERIO ST 91405
Certificate Information: 14417 W VALERIO ST 91405
- Application / Permit
- 20016-10000-17755
- Plan Check / Job No.
- B20LA13119
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93 USING SPECIAL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 10/6/2020
- Issuing Office
- Current Status
- CofC Issued on 4/16/2021
Permit Application Status History
| Submitted | 7/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2020 | HANS SANTIAGO |
| Plan Check Approved | 7/24/2020 | ANDREW SANTIAGO |
| Issued | 10/6/2020 | APPLICANT |
| OK for CofC | 2/26/2021 | KENNETH ROBERTS |
| CofC Issued | 4/16/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/22/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 11/25/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 12/2/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 12/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 12/9/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 12/16/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/16/2020 | Approved | JOE VELASQUEZ |
| Insulation | 12/18/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 12/23/2020 | Approved | DANIEL VARNUM |
| Final | 1/20/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| METHANE-Final | 1/20/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 1/20/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 2/26/2021 | OK for CofC | KENNETH ROBERTS |
| METHANE-Final | 2/26/2021 | Approved | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 2/26/2021 | Approved | KENNETH ROBERTS |