12905 W RIVERSIDE DR 91423

Certificate Information: 12905 W RIVERSIDE DR 91423

Application / Permit
20016-10000-17742
Plan Check / Job No.
B20LA13108
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Grocery Store
Work Description
INTERIOR TI TO EXISTING GROCERY STORE "WHOLE FOODS." SCOPE OF WORK INCLUDES ADDITION OF CEILING GRID STEEL FRAMING SYSTEM, NEW NON-BEARING WALLS AND CEILINGS AND REINFORCE (E) ROOF/MEZZ FRAMING FOR (N) EQUIPMENT.
Permit Issued
Issued on 12/29/2020
Issuing Office
Current Status
Permit Finaled on 1/21/2022

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 EUGENE BARBEAU
Disabled Access Plans Picked Up 8/18/2020 APPLICANT
Corrections Issued 8/21/2020 EUGENE BARBEAU
Quality Review Completed 8/31/2020 ALLEN MANALANSAN
Building Plans Picked Up 9/4/2020 APPLICANT
Green Plans Picked Up 12/9/2020 APPLICANT
Plan Check Approved 12/28/2020 EUGENE BARBEAU
Issued 12/29/2020 APPLICANT
Permit Finaled 1/21/2022 ROBERT DAVIS

Permit Application Clearance Information

"Q" conditions Cleared 10/21/2020 TERRI OSBORNE
Green Code Cleared 11/5/2020 EUGENE BARBEAU
DAS Clearance Cleared 12/3/2020 EUGENE BARBEAU
Food Service Establishment Cleared 12/22/2020 RAMESHBHAIR PATEL
Food establishment approval Cleared 12/28/2020 LACDHS APPROVED

Contact Information

Architect Meyer,, Mariah B; Lic. No.: C37440 8131 METCALF, SUITE 300      OVERLAND PARK, KS 66204
Contractor Savant Construction Inc; Lic. No.: 596646-B 13830 MOUNTAIN AVENUE      CHINO, CA 91710
Engineer Flanagan,, Joseph Neil; Lic. No.: C58349 930 CENTRAL      KANSAS CITY, MO 64105

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2021 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/7/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 1/7/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 1/8/2021 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/14/2021 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/15/2021 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 1/15/2021 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 1/21/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 1/26/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 1/26/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 1/27/2021 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 1/27/2021 Partial Approval ROBERT DAVIS
Deputy Steel/Welding 2/2/2021 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 2/4/2021 Conditional Approval ROBERT DAVIS
Wood Frame 2/4/2021 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 2/16/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/17/2021 Conditional Approval ROBERT DAVIS
Drywall Nailing 2/22/2021 Partial Approval ROBERT DAVIS
Insulation 2/22/2021 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 2/22/2021 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 2/26/2021 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/1/2021 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/3/2021 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 3/3/2021 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/4/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 3/4/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/5/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/10/2021 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 3/12/2021 Conditional Approval ROBERT DAVIS
Insulation 3/16/2021 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 3/16/2021 Partial Inspection JEFFREY FULTON
Wood Frame 3/16/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 3/22/2021 Partial Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/23/2021 Approved ROBERT DAVIS
Insulation 3/24/2021 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 3/25/2021 Partial Approval ROBERT DAVIS
Insulation 3/25/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 3/26/2021 Partial Approval ROBERT DAVIS
Insulation 3/26/2021 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 3/26/2021 Partial Approval ROBERT DAVIS
Wood Frame 3/26/2021 Conditional Approval ROBERT DAVIS
Insulation 3/31/2021 Approved ROBERT DAVIS
Light Gage Steel Frame 3/31/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Steel/Welding 4/6/2021 Conditional Approval ANDREW DORSO
Light Gage Steel Frame 4/6/2021 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 4/7/2021 Conditional Approval ROBERT DAVIS
Drywall Nailing 4/7/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Steel/Welding 4/8/2021 Approved ROBERT DAVIS
Drywall Nailing 4/15/2021 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 4/16/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 4/21/2021 Approved ROBERT DAVIS
Light Gage Steel Frame 4/27/2021 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 5/6/2021 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 5/7/2021 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 5/7/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 5/10/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 5/13/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 5/14/2021 Conditional Approval ROBERT DAVIS
Interior/Exterior Lathing 5/27/2021 Approved ROBERT DAVIS
T-Bar Ceiling 5/27/2021 Approved ROBERT DAVIS
Interior/Exterior Lathing 6/11/2021 Not Ready for Inspection ANDREW DORSO
Interior/Exterior Lathing 6/18/2021 Partial Approval ROBERT DAVIS
Posting Pre-Inspection 8/5/2021 No Access for Inspection DANIEL VARNUM
Posting Pre-Inspection 8/9/2021 Approved ROBERT DAVIS
Posting Pre-Inspection 9/17/2021 Partial Inspection ROBERT DAVIS
Final 10/28/2021 Not Ready for Inspection ROBERT DAVIS
Green Building Final 10/28/2021 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Approved ROBERT DAVIS
Smoke Detectors 10/28/2021 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 1/7/2022 Partial Inspection ROBERT DAVIS
Final 1/19/2022 Not Ready for Inspection ROBERT DAVIS
Smoke Detectors 1/19/2022 Approved ROBERT DAVIS
Final 1/21/2022 Permit Finaled ROBERT DAVIS