3903 N PORTOLA AVE 90032

Certificate Information: 3903 N PORTOLA AVE 90032

Application / Permit
20016-10000-17723
Plan Check / Job No.
B20LA13085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR/EXTERIOR REMODEL-CONVERT LIVING ROOM TO A BEDROOM, RELOCATE LAUNDRY, OPEN KITCHEN & LIVING ROOM AREA, CONVERT LAUNDRY TO A BATHROOM, KITCHEN REMODEL. RETROFIT 10 WINDOWS AND 12 DOORS, REMOVE AND REPLACE PORCH ROOF.
Permit Issued
Issued on 9/17/2020
Issuing Office
Metro
Current Status
Permit Finaled on 2/20/2021

Permit Application Status History

Submitted 7/27/2020 APPLICANT
Assigned to Plan Check Engineer 7/29/2020 LUKE GONZALES
Corrections Issued 7/29/2020 LUKE GONZALES
Plan Check Approved 9/9/2020 RICARDO RAMIREZ
Building Plans Picked Up 9/11/2020 APPLICANT
Issued 9/17/2020 APPLICANT
Permit Finaled 2/19/2021 COREY HUPP

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/12/2020 CELINA MORENO
Sewer availability Cleared 8/12/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/13/2020 CELINA MORENO
"D" conditions Cleared 8/20/2020 ANACANY HURTADO
"Q" conditions Cleared 8/20/2020 ANACANY HURTADO
Grading Pre-Inspection Cleared 8/26/2020 BARTON HOLMES

Contact Information

Contractor Emmental Construction Group Inc; Lic. No.: 1011107-B 9668 MILLIKEN AVE   STE 104-284    RANCHO CUCAMONGA, CA 91730
Engineer Yassin,, Diaa Aldin; Lic. No.: C56295 2939 CAMINO DEL TOMASINI      HACIENDA HEIGHTS, CA 91745

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 9/23/2020 No Access for Inspection COREY HUPP
ELECTRICAL-Rough 9/29/2020 Corrections Issued RUBEN SALAS
HVAC-Rough 9/29/2020 Corrections Issued RUBEN SALAS
PLUMBING-Rough 9/29/2020 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 10/6/2020 Not Ready for Inspection COREY HUPP
Deputy Drilled-In Anchors 10/9/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 10/13/2020 Approved COREY HUPP
Rough-Elec/Plmb/HVAC 10/13/2020 Partial Approval COREY HUPP
Drywall Nailing 10/20/2020 Approved COREY HUPP
Interior/Exterior Lathing 10/20/2020 Partial Approval COREY HUPP
Interior/Exterior Lathing 11/2/2020 Approved COREY HUPP
Shower Pan 11/2/2020 Approved COREY HUPP
Final 1/25/2021 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 1/25/2021 SGSOV Approved COREY HUPP
Smoke Detectors 1/25/2021 Approved COREY HUPP
Final 2/11/2021 Partial Inspection COREY HUPP
Final 2/19/2021 Permit Finaled COREY HUPP