1609 S WESTWOOD BLVD 90024
Certificate Information: 1609 S WESTWOOD BLVD 90024
- Application / Permit
- 20016-10000-17667
- Plan Check / Job No.
- B20LA13024
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT (ADA) WITH - ADDING ELEVATOR, REPLACING EXISTING STAIRCASE & ADA BATHROOMS. NO CHANGE IN FLOOR AREA.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/6/2024
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | ZAW HAN |
| Corrections Issued | 8/24/2020 | ZAW HAN |
| Disabled Access Plans Picked Up | 9/2/2020 | APPLICANT |
| Quality Review Completed | 9/25/2020 | TU HUA |
| Applicant returned to address corrections | 12/1/2020 | ZAW HAN |
| Applicant returned to address corrections | 3/5/2021 | ZAW HAN |
| Plan Check Approved | 3/8/2021 | ZAW HAN |
| Issued | 5/20/2021 | APPLICANT |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| Permit Finaled | 6/4/2024 | RICARDO ROBLES |
Permit Application Clearance Information
| Green Code | Cleared | 12/15/2020 | ZAW HAN |
| DAS Clearance | Cleared | 1/14/2021 | ZAW HAN |
| Supp. Use District POD/CDO/TDO | Cleared | 1/19/2021 | DYLAN SITTIG |
| Sewer availability | Cleared | 1/27/2021 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | NIKTA MOUSAVI |
| Highway dedication | Cleared | 2/18/2021 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 2/22/2021 | FREDDY GARCIA |
Contact Information
| Contractor | Aram Construction Company; Lic. No.: 934479-B | 8500 WILSHIRE BLVD # 509 BEVERLY HILLS, CA 90211 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/19/2022 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 5/6/2022 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 5/11/2022 | Corrections Issued | PAUL DAVIDSON |
| Wood Frame | 5/11/2022 | Conditional Approval | PAUL DAVIDSON |
| Special/Order Compliance | 2/13/2023 | Partial Inspection | PAUL DAVIDSON |
| Wood Frame | 2/20/2024 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 2/28/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Insulation | 2/28/2024 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 3/5/2024 | Partial Approval | RICARDO ROBLES |
| Interior/Exterior Lathing | 3/5/2024 | Approved | RICARDO ROBLES |
| Drywall Nailing | 3/15/2024 | Approved | RICARDO ROBLES |
| Final | 6/4/2024 | Permit Finaled | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV No Gas | RICARDO ROBLES |
| Smoke Detectors | 6/4/2024 | Approved | RICARDO ROBLES |