8111 N TILDEN AVE 91402
Certificate Information: 8111 N TILDEN AVE 91402
- Application / Permit
- 20016-10000-17617
- Plan Check / Job No.
- B20LA12970
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage and storage to ADU.
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | JOE VO |
| Corrections Issued | 8/25/2020 | JOE VO |
| Quality Review Completed | 9/4/2020 | MINYE PAK |
| Plan Check Approved | 2/10/2021 | JOE VO |
| Issued | 2/18/2021 | APPLICANT |
| CofO in Progress | 8/26/2022 | GREGG CUMMINGS |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/16/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 12/16/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/1/2021 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 9/2/2021 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/3/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/3/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/3/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 3/3/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 3/3/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 3/3/2022 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 3/8/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 3/11/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 3/11/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/29/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/29/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/4/2022 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/11/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/20/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/9/2022 | Conditional Approval | WILLIAM WREN |
| Insulation | 5/31/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Partial Approval | DAVID MATSON |
| Drywall Nailing | 6/24/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 7/1/2022 | Corrections Issued | GREGG CUMMINGS |
| Shower Pan | 7/7/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/9/2022 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 8/9/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/15/2022 | No Access for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/15/2022 | No Access for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 8/15/2022 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/17/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/17/2022 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 8/17/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/26/2022 | Approved | GREGG CUMMINGS |
| Final | 8/26/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 8/26/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/26/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 8/26/2022 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 8/26/2022 | Approved | GREGG CUMMINGS |