2817 S 3RD AVE 90018

Certificate Information: 2817 S 3RD AVE 90018

Application / Permit
20016-10000-17610
Plan Check / Job No.
B20LA12963
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached recreation room into ADU.
Permit Issued
Issued on 11/2/2020
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 JOE VO
Corrections Issued 8/27/2020 JOE VO
Quality Review Completed 9/4/2020 MINYE PAK
Applicant returned to address corrections 9/23/2020 JOE VO
Plan Check Approved 10/14/2020 JOE VO
Issued 11/2/2020 APPLICANT
CofO in Progress 7/29/2022 STUART CHAPMAN
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/30/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/30/2020 RENZ SORIANO
Sewer availability Cleared 9/30/2020 RENZ SORIANO
HPOZ Cleared 10/5/2020 MAX LODER
Historic monument Cleared 10/5/2020 MAX LODER
ZI Cleared 10/5/2020 MAX LODER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/1/2021 No Access for Inspection STUART CHAPMAN
ELECTRICAL-Rough 9/8/2021 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Partial Approval ALAN MORELOS
HVAC-Rough 9/8/2021 Corrections Issued ALAN MORELOS
PLUMBING-Rough 9/8/2021 Corrections Issued ALAN MORELOS
BUILDING-Rough-Frame 9/29/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 9/29/2021 Approved STUART CHAPMAN
Green Building Rough 9/29/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/29/2021 Approved STUART CHAPMAN
METHANE-Rough 9/29/2021 Approved STUART CHAPMAN
PLUMBING-Rough 9/29/2021 Approved STUART CHAPMAN
Insulation 10/15/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/15/2021 Partial Approval STUART CHAPMAN
Special/Order Compliance 10/15/2021 Approved HECTOR ALIKHAN
Drywall Nailing 11/24/2021 Approved STUART CHAPMAN
Final 6/13/2022 Corrections Issued STUART CHAPMAN
Smoke Detectors 6/13/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/12/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 7/29/2022 Approved STUART CHAPMAN
Final 7/29/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 7/29/2022 Approved STUART CHAPMAN
PLUMBING-Final 7/29/2022 Approved STUART CHAPMAN
Service/Power Release 7/29/2022 Approved STUART CHAPMAN