4504 N VARNA AVE 91423

Certificate Information: 4504 N VARNA AVE 91423

Application / Permit
20016-10000-17595
Plan Check / Job No.
B20LA12960
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. ADU CONVERSION. TO CONVERT EXISTING 20'-0"X29'-0" DETTACHED TWO CAR GARAGE TO ACCESSORY DWELLING UNIT (ADU)
Permit Issued
Issued on 6/14/2021
Issuing Office
Current Status
CofO Issued on 6/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 ARSALAN SHABESTARI
Corrections Issued 8/25/2020 ARSALAN SHABESTARI
Quality Review Completed 9/13/2020 PRANITA SHAH
Plan Check Approved 6/7/2021 ARSALAN SHABESTARI
Issued 6/14/2021 APPLICANT
CofO in Progress 6/23/2023 JOHN COLEMAN
CofO Issued 6/23/2023 MICHAEL SMITH
Permit Finaled 6/23/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/22/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 10/22/2020 GUILLERMO PETRA
Sewer availability Cleared 10/22/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/23/2020 GUILLERMO PETRA
ZI Cleared 11/23/2020 TERRI OSBORNE
Construction near power lines Cleared 2/6/2021 RIDWAN HARDY
Construction within easement Cleared 2/6/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/15/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/15/2021 Partial Approval MISAEL ESPARZA
Sewer 10/15/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 10/19/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/4/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/4/2021 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 11/4/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/14/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/14/2021 Corrections Issued MISAEL ESPARZA
Wood Frame 12/14/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/28/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 12/28/2021 Partial Approval THOMAS FINNILA
Green Building Rough 12/28/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 12/28/2021 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 1/4/2022 Partial Approval MATT KELLERMAN
Green Building Rough 1/18/2022 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 1/18/2022 Partial Approval MISAEL ESPARZA
Pre-Inspection 1/18/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 1/20/2022 No Access for Inspection MISAEL ESPARZA
HVAC-Rough 1/20/2022 No Access for Inspection MISAEL ESPARZA
PLUMBING-Rough 1/20/2022 No Access for Inspection MISAEL ESPARZA
Wood Frame 1/20/2022 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 1/25/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 1/25/2022 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 1/25/2022 Approved MISAEL ESPARZA
Wood Frame 1/25/2022 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 3/14/2022 Approved MISAEL ESPARZA
Insulation 3/14/2022 Approved MISAEL ESPARZA
Wood Frame 3/14/2022 Approved MISAEL ESPARZA
Drywall Nailing 5/11/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/12/2023 Corrections Issued JOHN COLEMAN
Final 6/12/2023 Corrections Issued JOHN COLEMAN
Green Building Final 6/12/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 6/12/2023 Approved JOHN COLEMAN
PLUMBING-Final 6/12/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 6/22/2023 Approved JOHN COLEMAN
Final 6/22/2023 Partial Inspection JOHN COLEMAN
Green Building Final 6/22/2023 Approved JOHN COLEMAN
HVAC-Final 6/22/2023 Approved JOHN COLEMAN
PLUMBING-Final 6/22/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 6/23/2023 Approved JOHN COLEMAN
Final 6/23/2023 OK to Issue CofO JOHN COLEMAN
Green Building Rough 6/23/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Approved JOHN COLEMAN
Smoke Detectors 6/23/2023 Approved JOHN COLEMAN