5630 1/2 N RANCHITO AVE 91401
Certificate Information: 5630 1/2 N RANCHITO AVE 91401
- Application / Permit
- 20016-10000-17594
- Plan Check / Job No.
- B20LA12959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. ADU. CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT PER ORDINANCE. SCOPE WILL ALSO CONSIST OF A (8' X 18') ADDITION. "COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 06/26/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 4/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | MICHAEL LOPEZ |
| Corrections Issued | 8/20/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 9/13/2020 | PRANITA SHAH |
| Plan Check Approved | 10/6/2020 | MICHAEL LOPEZ |
| Issued | 8/9/2021 | APPLICANT |
| CofO in Progress | 3/9/2022 | RICHARD DOCKUS |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| CofO Issued | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/24/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | M D H Builders / Design / Development; Lic. No.: 1067773-B | 6700 FALLBROOK AVE STE 100 WEST HILLS, CA 91307 |
| Engineer | Samadzadeh,, Ali Reza; Lic. No.: NA87661 | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 8/27/2021 | Approved | RICHARD DOCKUS |
| Sewer | 8/27/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/3/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 9/3/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/3/2021 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 9/3/2021 | Approved | RICHARD DOCKUS |
| Sewer | 9/3/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/8/2021 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 9/8/2021 | Approved | RICHARD DOCKUS |
| Insulation | 9/8/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 9/15/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/20/2021 | Approved | MICHEL ABAJAN |
| Final | 2/16/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/16/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 2/16/2022 | Approved | MISAEL ESPARZA |
| Final | 3/8/2022 | OK to Issue CofO | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | RICHARD DOCKUS |