19172 W DELANO ST 91335
Certificate Information: 19172 W DELANO ST 91335
- Application / Permit
- 20016-10000-17593
- Plan Check / Job No.
- B20LA12958
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) GARAGE & ADDITION FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d)
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | LAMAR DAVIS |
| Corrections Issued | 8/18/2020 | LAMAR DAVIS |
| Quality Review Completed | 9/1/2020 | TU HUA |
| Applicant returned to address corrections | 10/30/2020 | LAMAR DAVIS |
| Plan Check Approved | 1/7/2021 | LAMAR DAVIS |
| Issued | 1/21/2021 | APPLICANT |
| CofO in Progress | 9/20/2021 | STEVEN BACK |
| Permit Finaled | 9/21/2021 | MICHAEL SMITH |
| CofO Issued | 9/21/2021 | MICHAEL SMITH |
| Permit Finaled | 9/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/25/2020 | MARTIN FRAGOSO |
| Address approval | Cleared | 8/28/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/24/2020 | ADRIAN CASTRO |
| ZI | Cleared | 9/24/2020 | LAUREN PADICK |
| Construction near power lines | Cleared | 12/10/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/10/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2021 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 2/23/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 2/24/2021 | Corrections Issued | PAUL CHOPP |
| Sewer | 2/24/2021 | Approved | PAUL CHOPP |
| Underground Mechanical | 2/24/2021 | Corrections Issued | PAUL CHOPP |
| PLUMBING-Rough | 3/3/2021 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 3/5/2021 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 3/11/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | STEVEN BACK |
| Green Building Rough | 3/30/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 4/5/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 4/5/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 4/5/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | STEVEN BACK |
| Green Building Rough | 4/7/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 4/7/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/7/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 4/19/2021 | Partial Approval | STEVEN BACK |
| Insulation | 4/19/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 4/19/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 4/19/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Not Ready | STEVEN BACK |
| Drywall Nailing | 8/11/2021 | Approved | STEVEN BACK |
| Final | 8/11/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 8/11/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/11/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 8/11/2021 | Approved | STEVEN BACK |
| Final | 9/13/2021 | Corrections Issued | STEVEN BACK |
| Final | 9/20/2021 | OK to Issue CofO | STEVEN BACK |