4238 W AVENUE 40 90065

Certificate Information: 4238 W AVENUE 40 90065

Application / Permit
20016-10000-17396
Plan Check / Job No.
B20LA12800
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING GARAGE TO ADU PER ORDINANCE AND LAMC (12.22 A33)
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 MAHNAZ NOURHASHEMI
Corrections Issued 8/21/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 8/25/2020 JASON HEALEY
Building Plans Picked Up 9/4/2020 APPLICANT
Applicant returned to address corrections 8/23/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 3/1/2022 MAHNAZ NOURHASHEMI
Plan Check Approved 3/1/2022 MAHNAZ NOURHASHEMI
Issued 3/1/2022 APPLICANT
CofO in Progress 1/8/2024 CRAIG VAUGHAN
Permit Finaled 9/17/2024 DEROLD HAUFF
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/24/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 3/24/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/30/2021 WALLIE JONG
Sewer availability Cleared 3/30/2021 WALLIE JONG
Hydrant and Access approval Cleared 7/29/2021 MATTHEW CRAIG
ZI Cleared 8/13/2021 ADRINEH MELKONIAN
Low Impact Development Cleared 9/8/2021 YVAINNE GALSIM
Construction near power lines Cleared 10/12/2021 RIDWAN HARDY
Low Impact Development Cleared 2/3/2022 TA ANH
GPI Written Notices Cleared 2/11/2022 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 2/11/2022 MAHNAZ NOURHASHEMI

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3627 E FIRST STREET      LOS ANGELES, CA 90063
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/22/2022 Corrections Issued SCOTT FINNILA
Sewer 3/22/2022 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 4/25/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 4/25/2022 Partial Approval CRAIG VAUGHAN
Sewer 4/25/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/27/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/16/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 8/16/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 8/16/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 8/16/2022 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 8/16/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 8/16/2022 Not Ready for Inspection CRAIG VAUGHAN
Sewer 8/16/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 10/14/2022 Not Ready for Inspection CRAIG VAUGHAN
Sewer 10/14/2022 Partial Approval CRAIG VAUGHAN
Gas Test 10/19/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 10/19/2022 Corrections Issued KATHRYN BUTTERWORTH
Underground Mechanical 10/25/2022 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/15/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 12/15/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 12/15/2022 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 12/15/2022 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 12/15/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 12/15/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 1/11/2023 Corrections Issued CRAIG VAUGHAN
Gas Test 1/11/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/11/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 1/13/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 1/13/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 1/13/2023 Approved CRAIG VAUGHAN
Green Building Rough 1/13/2023 Approved CRAIG VAUGHAN
HVAC-Rough 1/13/2023 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 1/13/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 1/13/2023 Corrections Issued CRAIG VAUGHAN
Sewer 1/13/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 1/25/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 1/25/2023 Partial Approval CRAIG VAUGHAN
Gas Test 1/25/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 1/25/2023 Approved CRAIG VAUGHAN
Sewer 1/25/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 2/1/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/1/2023 Approved CRAIG VAUGHAN
Sewer 2/1/2023 Approved CRAIG VAUGHAN
Insulation 2/7/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 2/7/2023 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 2/24/2023 Approved HAMIK HARTOUNIAN
Final 10/31/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/31/2023 Approved CRAIG VAUGHAN
MERV13>=Final 10/31/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/31/2023 Corrections Issued CRAIG VAUGHAN
Final 11/16/2023 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 11/16/2023 Approved BRIAN SULLIVAN
Final 11/20/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 1/5/2024 Approved CRAIG VAUGHAN
Final 1/5/2024 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 1/5/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 1/5/2024 Approved CRAIG VAUGHAN