1241 1/2 N CITRUS AVE 90038
Certificate Information: 1241 1/2 N CITRUS AVE 90038
- Application / Permit
- 20016-10000-17395
- Plan Check / Job No.
- B20LA12798
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | JOE VO |
| Corrections Issued | 8/3/2020 | JOE VO |
| Quality Review Completed | 8/13/2020 | MINYE PAK |
| Plan Check Approved | 11/19/2020 | JOE VO |
| Issued | 12/21/2020 | APPLICANT |
| CofO in Progress | 12/31/2022 | JOAQUIN GREENOUGH |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/4/2020 | MICHAEL SOTO |
| Address approval | Cleared | 8/12/2020 | ELAINE LEI |
| Sewer availability | Cleared | 8/12/2020 | ELAINE LEI |
| Construction near power lines | Cleared | 11/17/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2020 | ELAINE LEI |
Contact Information
| Contractor | Corro Construction; Lic. No.: 524225-B | 1347 HEPNER AVE LOS ANGELES, CA 90041 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/4/2021 | No Access for Inspection | RICHARD STEINBACH |
| Sewer | 1/6/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/13/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/25/2021 | Corrections Issued | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 2/1/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 2/1/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/18/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/9/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 3/9/2021 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 3/16/2021 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 4/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 4/15/2021 | No Access for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 6/22/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 6/22/2021 | Partial Approval | BRIAN SULLIVAN |
| Wood Frame | 6/22/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 7/7/2021 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 7/9/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 7/9/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 7/9/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/10/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Final | 8/10/2021 | Partial Approval | RAUL BARAJAS |
| Sewer | 8/10/2021 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/11/2022 | Approved | FREDDIE RIVERA |
| Final | 8/11/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/11/2022 | Approved | FREDDIE RIVERA |
| Final | 9/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Pre-Inspection | 9/15/2022 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 9/20/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 12/21/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | JOAQUIN GREENOUGH |