539 N HAWAIIAN AVE 90744

Certificate Information: 539 N HAWAIIAN AVE 90744

Application / Permit
20016-10000-17360
Plan Check / Job No.
B20LA12774
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1. INTERIOR REMODEL EXISTING BATHROOM AND SPLIT INTO 2 BATHROOMS. ENDING WITH 2 BEDROOM 2BATH - NON BEARING - NO STRUCTURAL 1 OF 2
Permit Issued
Issued on 11/6/2020
Issuing Office
Current Status
Permit Finaled on 7/20/2021

Permit Application Status History

Submitted 8/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 TSE MING HUANG
Corrections Issued 8/21/2020 TSE MING HUANG
Applicant returned to address corrections 9/2/2020 TSE MING HUANG
Applicant returned to address corrections 9/14/2020 CRISTINA SALAZAR
Plan Check Approved 10/26/2020 TSE MING HUANG
Issued 11/6/2020 APPLICANT
Building Plans Picked Up 11/9/2020 APPLICANT
Permit Finaled 7/20/2021 BRIAN CHRISTIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/9/2020 ERIK BEASLEY
Sewer availability Cleared 10/9/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Shykowski,, Jason Antony; Lic. No.: C58234 810 BRIDLE PATH RD      COLFAX, CA 95713

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/8/2021 Approved BRIAN CHRISTIAN
Sewer 3/8/2021 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 3/9/2021 Corrections Issued BRIAN CHRISTIAN
Underground Mechanical 3/9/2021 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 3/11/2021 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Rough 3/18/2021 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 3/26/2021 Approved PAUL BECKER
Deputy Wood Construction 3/26/2021 No Access for Inspection PAUL BECKER
HVAC-Rough 3/26/2021 Approved PAUL BECKER
PLUMBING-Rough 3/26/2021 Approved PAUL BECKER
Insulation 3/31/2021 Approved BRIAN CHRISTIAN
Drywall Nailing 4/6/2021 Corrections Issued BRIAN CHRISTIAN
Interior/Exterior Lathing 4/6/2021 Corrections Issued BRIAN CHRISTIAN
Drywall Nailing 4/8/2021 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/8/2021 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 6/30/2021 Corrections Issued BRIAN CHRISTIAN
Final 6/30/2021 Not Ready for Inspection BRIAN CHRISTIAN
Green Building Final 6/30/2021 Approved BRIAN CHRISTIAN
HVAC-Final 6/30/2021 Not Ready for Inspection BRIAN CHRISTIAN
PLUMBING-Final 6/30/2021 Corrections Issued BRIAN CHRISTIAN
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Approved BRIAN CHRISTIAN
Smoke Detectors 6/30/2021 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 7/8/2021 Not Ready for Inspection BRIAN CHRISTIAN
Final 7/8/2021 Not Ready for Inspection BRIAN CHRISTIAN
PLUMBING-Final 7/8/2021 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Final 7/20/2021 Approved BRIAN CHRISTIAN
Final 7/20/2021 Permit Finaled BRIAN CHRISTIAN
PLUMBING-Final 7/20/2021 Approved BRIAN CHRISTIAN