539 N HAWAIIAN AVE 90744
Certificate Information: 539 N HAWAIIAN AVE 90744
- Application / Permit
- 20016-10000-17360
- Plan Check / Job No.
- B20LA12774
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1. INTERIOR REMODEL EXISTING BATHROOM AND SPLIT INTO 2 BATHROOMS. ENDING WITH 2 BEDROOM 2BATH - NON BEARING - NO STRUCTURAL 1 OF 2
- Permit Issued
- Issued on 11/6/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/20/2021
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | TSE MING HUANG |
| Corrections Issued | 8/21/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 9/2/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 9/14/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 10/26/2020 | TSE MING HUANG |
| Issued | 11/6/2020 | APPLICANT |
| Building Plans Picked Up | 11/9/2020 | APPLICANT |
| Permit Finaled | 7/20/2021 | BRIAN CHRISTIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/9/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shykowski,, Jason Antony; Lic. No.: C58234 | 810 BRIDLE PATH RD COLFAX, CA 95713 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/8/2021 | Approved | BRIAN CHRISTIAN |
| Sewer | 3/8/2021 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 3/9/2021 | Corrections Issued | BRIAN CHRISTIAN |
| Underground Mechanical | 3/9/2021 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 3/11/2021 | Not Ready for Inspection | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 3/18/2021 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | PAUL BECKER |
| Deputy Wood Construction | 3/26/2021 | No Access for Inspection | PAUL BECKER |
| HVAC-Rough | 3/26/2021 | Approved | PAUL BECKER |
| PLUMBING-Rough | 3/26/2021 | Approved | PAUL BECKER |
| Insulation | 3/31/2021 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 4/6/2021 | Corrections Issued | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/6/2021 | Corrections Issued | BRIAN CHRISTIAN |
| Drywall Nailing | 4/8/2021 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/8/2021 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 6/30/2021 | Corrections Issued | BRIAN CHRISTIAN |
| Final | 6/30/2021 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Green Building Final | 6/30/2021 | Approved | BRIAN CHRISTIAN |
| HVAC-Final | 6/30/2021 | Not Ready for Inspection | BRIAN CHRISTIAN |
| PLUMBING-Final | 6/30/2021 | Corrections Issued | BRIAN CHRISTIAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Approved | BRIAN CHRISTIAN |
| Smoke Detectors | 6/30/2021 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 7/8/2021 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Final | 7/8/2021 | Not Ready for Inspection | BRIAN CHRISTIAN |
| PLUMBING-Final | 7/8/2021 | Not Ready for Inspection | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 7/20/2021 | Approved | BRIAN CHRISTIAN |
| Final | 7/20/2021 | Permit Finaled | BRIAN CHRISTIAN |
| PLUMBING-Final | 7/20/2021 | Approved | BRIAN CHRISTIAN |