801 S HOPE ST Lobby 90017
Certificate Information: 801 S HOPE ST Lobby 90017
- Application / Permit
- 20016-10000-17343
- Plan Check / Job No.
- B20LA12737
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (13) Office
- Work Description
- RENOVATION RESIDENTIAL LOBBY: NEW PARTITIONS, NEW RECEPTION DESK, NEW FINISHES AND UPDATED LIGHTING. NO CHANGE OF EXISTING ENTRANCES AND EXITS, NO ADDED AREA.
- Permit Issued
- Issued on 11/5/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/4/2021
Permit Application Status History
| Submitted | 7/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | AMIR DANAI |
| Corrections Issued | 7/24/2020 | AMIR DANAI |
| Plan Check Approved | 8/19/2020 | JESSE JIMENEZ |
| Issued | 11/5/2020 | APPLICANT |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| Permit Finaled | 6/4/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| ZI | Cleared | 7/31/2020 | TERRI OSBORNE |
| Fire Marshall Fire Life Safety | Cleared | 8/11/2020 | VIDAL GARCIA |
Contact Information
| Architect | Hanson,, Douglas D; Lic. No.: C28709 | HANSON LA 2129 W. 20TH ST LOS ANGELES, CA 90018 |
| Contractor | Swinerton Builders; Lic. No.: 92-C21 | 260 TOWNSEND ST 5TH FL-LEGAL SAN FRANCISCO, CA 94107 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 12/22/2020 | Corrections Issued | KATY RAMIREZ |
| Insulation | 1/21/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 1/21/2021 | Partial Inspection | KATY RAMIREZ |
| Pre-Inspection | 1/22/2021 | No Access for Inspection | KATY RAMIREZ |
| Drywall Nailing | 2/2/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 2/2/2021 | Approved | KATY RAMIREZ |
| Drywall Nailing | 2/8/2021 | Partial Approval | KATY RAMIREZ |
| Final | 5/26/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Green Building Final | 5/26/2021 | Not Ready for Inspection | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 5/26/2021 | Approved | DANIEL COLLINS |
| Final | 6/2/2021 | Conditional Approval | DANIEL COLLINS |
| Green Building Final | 6/2/2021 | Approved | DANIEL COLLINS |
| Final | 6/4/2021 | Permit Finaled | DANIEL COLLINS |