832 W 25TH ST 90731
Certificate Information: 832 W 25TH ST 90731
- Application / Permit
- 20016-10000-17307
- Plan Check / Job No.
- B20LA12719
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 2nd floor Rec-room above detached garage to ADU.
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2020 | JOE VO |
| Corrections Issued | 8/20/2020 | JOE VO |
| Quality Review Completed | 9/4/2020 | MINYE PAK |
| Plan Check Approved | 9/11/2020 | JOE VO |
| Issued | 9/17/2020 | APPLICANT |
| CofO in Progress | 3/6/2023 | ANSON MAGLASANG |
| Permit Finaled | 3/6/2023 | ANSON MAGLASANG |
| CofO Issued | 3/6/2023 | ANSON MAGLASANG |
| Permit Finaled | 3/6/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2020 | CHINH DINH |
| Sewer availability | Cleared | 9/9/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2020 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 1/25/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/8/2021 | Approved | JOHN KLARIN |
| Final | 2/8/2021 | Not Ready for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 2/8/2021 | Approved | JOHN KLARIN |
| Final | 3/1/2021 | Not Ready for Inspection | JOHN KLARIN |
| Final | 3/10/2021 | Corrections Issued | JOHN KLARIN |
| Final | 3/24/2021 | Corrections Issued | JOHN KLARIN |
| Final | 5/19/2021 | Corrections Issued | JOHN KLARIN |
| Final | 11/7/2022 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 2/2/2023 | No Access for Inspection | JULIAN AMAYA |
| ELECTRICAL-Final | 2/6/2023 | Approved | JAMES CHAVEZ |
| Final | 3/3/2023 | OK to Issue CofO | JOHN KLARIN |