11865 W MAGNOLIA BLVD 91607
Certificate Information: 11865 W MAGNOLIA BLVD 91607
- Application / Permit
- 20016-10000-17171
- Plan Check / Job No.
- B20LA12626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93 - INSTALL (3) STEEL SPECIAL CANTILEVER COLUMNS
- Permit Issued
- Issued on 10/26/2020
- Issuing Office
- Current Status
- CofC Issued on 10/13/2021
Permit Application Status History
| Submitted | 7/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | YOUNG KIM |
| Corrections Issued | 7/25/2020 | YOUNG KIM |
| Quality Review Completed | 7/27/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/28/2020 | HANS SANTIAGO |
| Plan Check Approved | 10/2/2020 | ANDREW SANTIAGO |
| Issued | 10/26/2020 | APPLICANT |
| OK for CofC | 7/19/2021 | KENNETH ROBERTS |
| CofC Issued | 10/13/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/7/2020 | ANACANY HURTADO |
| Tenant Habitability Plan | Cleared | 10/19/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/29/2020 | Approved | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 11/19/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 11/24/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 11/25/2020 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 12/1/2020 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 12/3/2020 | Approved | RICKEY JACKSON |
| Deputy Other (see comments) | 12/7/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 12/7/2020 | Conditional Approval | DANIEL VARNUM |
| Structural Steel Frame | 12/14/2020 | Approved | HAMID PISHEHVAR |
| Wood Frame | 12/14/2020 | Approved | HAMID PISHEHVAR |
| Interior/Exterior Lathing | 12/30/2020 | Approved | DANIEL VARNUM |
| Final | 4/5/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 4/5/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 7/19/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 7/19/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 7/19/2021 | Approved | KENNETH ROBERTS |