5190 1/2 N CASPAR AVE 90041
Certificate Information: 5190 1/2 N CASPAR AVE 90041
- Application / Permit
- 20016-10000-17057
- Plan Check / Job No.
- B20LA12550
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPlan. Convert existing garage and storage building to detached ADU per state law GCS 65852.2(e)(1)(A). All works per WFPP.
- Permit Issued
- Issued on 2/11/2021
- Issuing Office
- Current Status
- CofO Issued on 12/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | HELEN NGUYEN |
| Corrections Issued | 8/17/2020 | HELEN NGUYEN |
| Quality Review Completed | 9/13/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 10/21/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/16/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/8/2021 | HELEN NGUYEN |
| Plan Check Approved | 1/15/2021 | HELEN NGUYEN |
| Issued | 2/11/2021 | APPLICANT |
| CofO in Progress | 10/19/2021 | CRAIG VAUGHAN |
| CofO Issued | 12/14/2022 | DEROLD HAUFF |
| Permit Finaled | 12/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/22/2020 | PATRICK MISCHLICH |
| Address approval | Cleared | 9/29/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/29/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 10/13/2020 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 10/21/2020 | PRANITA SHAH |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2020 | PAMELA TENEZA |
Contact Information
| Contractor | Ground Up Builders And Design Inc; Lic. No.: 911849-B | 14545 VICTORY BLVD STE 601 VAN NUYS, CA 91411 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2021 | Partial Approval | CRAIG VAUGHAN |
| Pre-Inspection | 4/9/2021 | Partial Inspection | CRAIG VAUGHAN |
| Gas Test | 5/21/2021 | Not Ready for Inspection | SHAWN ESHBACH |
| PLUMBING-Rough | 5/21/2021 | Partial Approval | SHAWN ESHBACH |
| Rough-Elec/Plmb/HVAC | 5/21/2021 | Corrections Issued | SHAWN ESHBACH |
| Wood Frame | 5/21/2021 | Approved | SHAWN ESHBACH |
| ELECTRICAL-Rough | 6/10/2021 | Approved | CRAIG VAUGHAN |
| Gas Test | 6/10/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 6/10/2021 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/10/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/10/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 6/10/2021 | Approved | CRAIG VAUGHAN |
| Gas Test | 6/17/2021 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 6/17/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 6/17/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 7/13/2021 | Approved | THOMAS LOGRASSO |
| Shower Pan | 7/13/2021 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/15/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/15/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/15/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Approved | BRIAN SULLIVAN |
| Pre-Inspection | 8/30/2021 | Partial Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 10/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 10/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 10/18/2021 | OK to Issue CofO | CRAIG VAUGHAN |