5190 1/2 N CASPAR AVE 90041

Certificate Information: 5190 1/2 N CASPAR AVE 90041

Application / Permit
20016-10000-17057
Plan Check / Job No.
B20LA12550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPlan. Convert existing garage and storage building to detached ADU per state law GCS 65852.2(e)(1)(A). All works per WFPP.
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 12/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 HELEN NGUYEN
Corrections Issued 8/17/2020 HELEN NGUYEN
Quality Review Completed 9/13/2020 PRANITA SHAH
Applicant returned to address corrections 10/21/2020 HELEN NGUYEN
Applicant returned to address corrections 12/16/2020 HELEN NGUYEN
Applicant returned to address corrections 1/8/2021 HELEN NGUYEN
Plan Check Approved 1/15/2021 HELEN NGUYEN
Issued 2/11/2021 APPLICANT
CofO in Progress 10/19/2021 CRAIG VAUGHAN
CofO Issued 12/14/2022 DEROLD HAUFF
Permit Finaled 12/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/22/2020 PATRICK MISCHLICH
Address approval Cleared 9/29/2020 JEANIE LAM
Sewer availability Cleared 9/29/2020 JEANIE LAM
Construction near power lines Cleared 10/13/2020 RIDWAN HARDY
GPI Written Notices Cleared 10/21/2020 PRANITA SHAH
Eng Process Fee Ord 176,300 Cleared 12/23/2020 PAMELA TENEZA

Contact Information

Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12631 IMPERIAL HWY F-230      SANTA FE SPRINGS, CA 90670

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2021 Partial Approval CRAIG VAUGHAN
Pre-Inspection 4/9/2021 Partial Inspection CRAIG VAUGHAN
Gas Test 5/21/2021 Not Ready for Inspection SHAWN ESHBACH
PLUMBING-Rough 5/21/2021 Partial Approval SHAWN ESHBACH
Rough-Elec/Plmb/HVAC 5/21/2021 Corrections Issued SHAWN ESHBACH
Wood Frame 5/21/2021 Approved SHAWN ESHBACH
ELECTRICAL-Rough 6/10/2021 Approved CRAIG VAUGHAN
Gas Test 6/10/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 6/10/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 6/10/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/10/2021 Partial Approval CRAIG VAUGHAN
Wood Frame 6/10/2021 Approved CRAIG VAUGHAN
Gas Test 6/17/2021 Partial Approval CRAIG VAUGHAN
HVAC-Rough 6/17/2021 Approved CRAIG VAUGHAN
Insulation 6/17/2021 Approved CRAIG VAUGHAN
Drywall Nailing 7/13/2021 Approved THOMAS LOGRASSO
Shower Pan 7/13/2021 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 7/15/2021 Approved CRAIG VAUGHAN
Green Building Rough 7/15/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/15/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Approved BRIAN SULLIVAN
Pre-Inspection 8/30/2021 Partial Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 10/8/2021 Approved CRAIG VAUGHAN
Final 10/8/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/8/2021 Approved CRAIG VAUGHAN
Final 10/18/2021 OK to Issue CofO CRAIG VAUGHAN