1759 W 35TH PL 90018
Certificate Information: 1759 W 35TH PL 90018
- Application / Permit
- 20016-10000-16994
- Plan Check / Job No.
- B20LA12498
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ALTERATION AND ADDITION TO AN (E) DUPLEX. RELOCATE STAIRCASE AND INTERIOR REMODEL INCLUDING, TWO NEW BATHROOMS, WINDOW CHANGE OUT SAME SIZE, CLOSE SOME EXISTING WINDOWS AT BOTH UNITS, AND ADD EXTERIOR STAIRS.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2020 | STANLEY RAAP |
| Corrections Issued | 8/17/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 9/22/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 10/16/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 11/10/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 11/10/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 11/12/2020 | APPLICANT |
| No Progress | 11/16/2020 | CRISTINA SALAZAR |
| Issued | 11/19/2020 | APPLICANT |
| CofO in Progress | 6/3/2021 | ROBERT MCDOWELL |
| No Progress | 3/14/2023 | RICHARD STEINBACH |
| CofO in Progress | 4/20/2023 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
| CofO Issued | 4/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 11/6/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/6/2020 | JEANIE LAM |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| HVAC-Rough | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| METHANE-Rough | 12/2/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| Wood Frame | 12/2/2020 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/11/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/11/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/11/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 3/11/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 3/11/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/11/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Final | 3/23/2021 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Green Building Final | 3/23/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 3/23/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 3/23/2021 | Approved | ROBERT MCDOWELL |
| METHANE-Subgrade | 3/23/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 3/23/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 3/23/2021 | Approved | ROBERT MCDOWELL |
| Final | 6/3/2021 | OK to Issue CofO | ROBERT MCDOWELL |