4315 S ROMA CT 90292

Certificate Information: 4315 S ROMA CT 90292

Application / Permit
20016-10000-16977
Plan Check / Job No.
B20LA12477
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF EXISTING 4,024 SF SINGLE FAMILY DWELLING. ADDING JADU WITHIN EXISTING FLOOR AREA. WORK INCLUDES NEW WINDOWS, REROOF, ELECTRICAL, MECHANICAL, AND PLUMBING. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 4/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 DANIEL YIP
Corrections Issued 8/14/2020 DANIEL YIP
Quality Review Completed 9/1/2020 HERNAN ARREOLA
Building Plans Picked Up 9/2/2020 APPLICANT
Plan Check Approved 11/24/2020 DANIEL YIP
Issued 1/12/2021 APPLICANT
CofO in Progress 4/5/2022 ANDREW NAVE
CofO in Progress 4/5/2022 ANDREW NAVE
Permit Finaled 4/6/2022 DANIEL ORRANTE
CofO Issued 4/6/2022 DANIEL ORRANTE
Permit Finaled 4/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 9/16/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/18/2020 DINAH GARIN
Specific Plan Cleared 10/23/2020 SIENNA KUO

Contact Information

Architect Adams,, Lauren Amanda; Lic. No.: C30146 8695 WASHINGTON BLVD SUITE 205      CULVER CITY, CA 90232
Contractor Gaia Construction Inc; Lic. No.: 912485-B 2800 GLENDON AVENUE      LOS ANGELES, CA 90064

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2021 Not Ready for Inspection JOHNNY MIRANDA
Pre-Inspection 2/26/2021 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 3/5/2021 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/8/2021 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 3/11/2021 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/16/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/16/2021 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/25/2021 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 3/26/2021 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/30/2021 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 4/5/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 4/5/2021 Partial Approval JOHNNY MIRANDA
Sewer 4/5/2021 Approved JOHNNY MIRANDA
Pre-Inspection 4/15/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Not Ready for Inspection JOHNNY MIRANDA
Structural Steel Frame 5/7/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 5/7/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 5/10/2021 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 6/2/2021 No Access for Inspection AMY COLIN
Deputy Wood Construction 6/2/2021 No Access for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/8/2021 Approved JOHNNY MIRANDA
HVAC-Rough 6/11/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 6/14/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 6/16/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 6/30/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 7/6/2021 Partial Approval PIERRE VEGA
Deputy Wood Construction 7/6/2021 Partial Approval PIERRE VEGA
HVAC-Rough 7/7/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 7/7/2021 Approved JOHNNY MIRANDA
Deputy Other (see comments) 7/8/2021 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Approved JOHNNY MIRANDA
HVAC-Rough 7/8/2021 Partial Approval JOHNNY MIRANDA
METHANE-Rough 7/8/2021 Approved JOHNNY MIRANDA
HVAC-Rough 7/19/2021 Approved JOHNNY MIRANDA
Insulation 7/22/2021 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 7/23/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 8/3/2021 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/6/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 8/6/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 8/10/2021 Partial Approval JOHNNY MIRANDA
Wood Frame 8/10/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 8/18/2021 Not Ready for Inspection KENNETH NAGLE
Insulation 8/18/2021 Not Ready for Inspection KENNETH NAGLE
Interior/Exterior Lathing 8/18/2021 Partial Approval KENNETH NAGLE
Wood Frame 8/18/2021 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 8/19/2021 Approved JOHNNY MIRANDA
Insulation 8/19/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/27/2021 Partial Approval JOHNNY MIRANDA
Drywall Nailing 8/30/2021 Not Ready for Inspection JOHNNY MIRANDA
Drywall Nailing 8/31/2021 Approved JOHNNY MIRANDA
Shower Pan 8/31/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/2/2021 Partial Approval KENNETH NAGLE
Service/Power Release 9/17/2021 Approved JOHNNY MIRANDA
Deputy Wood Construction 12/7/2021 No Access for Inspection DAVID FEILER
ELECTRICAL-Rough 1/13/2022 Partial Approval DAVID FEILER
Grounding or Bonding 1/13/2022 Not Ready for Inspection DAVID FEILER
Pool Piping 1/13/2022 Not Ready for Inspection DAVID FEILER
Pre-Gunite 1/13/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 2/14/2022 Corrections Issued DAVID FEILER
HVAC-Final 2/22/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Final 3/2/2022 Approved DAVID FEILER
ELECTRICAL-Final 3/25/2022 Conditional Approval PATRICK QUALEY
PLUMBING-Final 3/25/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 4/1/2022 Approved ANDREW NAVE
ELECTRICAL-Final 4/1/2022 Approved ANDREW NAVE
Final 4/1/2022 OK to Issue CofO ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 4/1/2022 Approved ANDREW NAVE