2711-2711 1/2 E 4TH ST 90063

Certificate Information: 2711-2711 1/2 E 4TH ST 90063

Application / Permit
20016-10000-16854
Plan Check / Job No.
B20LA12379
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF EXISTING GARAGE TO 2 ADU'S PER CA. GOVT. CODE 65852.2(e)(1)(D) and LAMC 12.22 A.33 (c)-(d), (g).
Permit Issued
Issued on 7/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/21/2020 FERNANDO FLORES
Corrections Issued 7/21/2020 FERNANDO FLORES
Applicant returned to address corrections 8/24/2021 JESSE JIMENEZ
Applicant returned to address corrections 3/3/2022 KHUONG TRUONG
Applicant returned to address corrections 3/24/2022 SHANGQIN XIE
Plan Check Approved 3/24/2022 SHANGQIN XIE
No Progress 3/29/2022 SHANGQIN XIE
Building Plans Picked Up 3/30/2022 APPLICANT
Plan Check Approved 5/3/2022 FERNANDO FLORES
Issued 7/7/2022 APPLICANT
CofO in Progress 5/13/2026 FREDDIE RIVERA
CofO Issued 5/14/2026 DEROLD HAUFF
Permit Finaled 5/14/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/3/2020 CELINA MORENO
Address approval Cleared 8/6/2020 CELINA MORENO
Highway dedication Cleared 8/6/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 8/6/2020 CELINA MORENO
Historic Resource Verification Cleared 8/20/2020 MICAELA TORRES-GIL
ZA Case Cleared 8/20/2020 JOE LUCKEY
ZI Cleared 8/20/2020 JOE LUCKEY
Sewer availability Cleared 8/21/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 8/24/2020 PATRICK MISCHLICH
Redevelopment Project Area Cleared 10/19/2020 DAVID URITA
GPI Written Notices Cleared 3/2/2022 FERNANDO FLORES

Contact Information

Architect Centuori,, Jeanine G; Lic. No.: C28180 670 MOULTON AVENUE # 7      LOS ANGELES, CA 90031
Contractor Owner-Builder       ,
Geologist Kaligi,, Azad Adam; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/25/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 10/25/2022 Not Ready for Inspection MARK FERRARI
METHANE-Barrier 10/25/2022 Not Ready for Inspection MARK FERRARI
METHANE-Subgrade 10/25/2022 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 2/7/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Barrier 2/7/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Subgrade 2/7/2023 Not Ready for Inspection JULIAN CAPUCETTI
Deputy Drilled-In Anchors 2/13/2023 Conditional Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 2/14/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Barrier 2/14/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Subgrade 2/14/2023 Not Ready for Inspection JULIAN CAPUCETTI
Deputy Methane Barrier 2/23/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 2/27/2023 Corrections Issued JULIAN CAPUCETTI
METHANE-Barrier 2/27/2023 Partial Approval JULIAN CAPUCETTI
METHANE-Rough 2/27/2023 Partial Approval JULIAN CAPUCETTI
METHANE-Subgrade 2/27/2023 Partial Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 4/12/2023 Corrections Issued JULIAN CAPUCETTI
METHANE-Barrier 4/12/2023 Approved JULIAN CAPUCETTI
METHANE-Subgrade 4/12/2023 Not Ready for Inspection JULIAN CAPUCETTI
Footing/Foundation/Slab 4/26/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Subgrade 4/26/2023 Not Ready for Inspection JULIAN CAPUCETTI
Footing/Foundation/Slab 4/28/2023 Corrections Issued VAHE KELEDJIAN
METHANE-Subgrade 4/28/2023 Partial Inspection VAHE KELEDJIAN
Excavation/Setback/Form/Re-Bar 6/2/2023 Partial Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 6/2/2023 Partial Approval JULIAN CAPUCETTI
METHANE-Subgrade 6/2/2023 Partial Approval JULIAN CAPUCETTI
Deputy Methane Barrier 8/9/2023 Conditional Approval JULIAN CAPUCETTI
METHANE-Subgrade 8/15/2023 Approved JULIAN CAPUCETTI
Deputy Drilled-In Anchors 11/8/2023 Conditional Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 11/9/2023 Approved RAMAZANALI ALMASI
Footing/Foundation/Slab 11/9/2023 Approved RAMAZANALI ALMASI
METHANE-Rough 11/9/2023 Approved RAMAZANALI ALMASI
Final 7/1/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 7/1/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Rough 7/1/2024 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 7/1/2024 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 7/1/2024 Not Ready for Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Approved RONALD JIMENEZ
Green Building Rough 7/30/2024 Approved RONALD JIMENEZ
Wood Frame 7/30/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 1/27/2025 Not Ready for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 1/27/2025 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 1/27/2025 Not Ready for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 2/7/2025 Conditional Approval FREDDIE RIVERA
Wood Frame 2/7/2025 Corrections Issued FREDDIE RIVERA
Wood Frame 2/25/2025 Approved FREDDIE RIVERA
Deputy Methane Barrier 4/15/2025 Conditional Approval FREDDIE RIVERA
Insulation 5/12/2025 Corrections Issued FREDDIE RIVERA
Drywall Nailing 6/9/2025 Approved JUSTIN HAWLEY
Insulation 6/9/2025 Approved JUSTIN HAWLEY
Special/Order Compliance 6/9/2025 Approved JUSTIN HAWLEY
Final 3/16/2026 Corrections Issued FREDDIE RIVERA
Green Building Final 3/16/2026 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 3/16/2026 Approved FREDDIE RIVERA
Special/Order Compliance 3/16/2026 Partial Inspection OSVALDO PARAMO
Final 4/7/2026 Corrections Issued FREDDIE RIVERA
Final 5/13/2026 OK to Issue CofO FREDDIE RIVERA