9462-9464 N ROSLYNDALE AVE 91331
Certificate Information: 9462-9464 N ROSLYNDALE AVE 91331
- Application / Permit
- 20016-10000-16834
- Plan Check / Job No.
- B20LA12368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Check. Convert existing attached (20' X 17'-11") garage into an accessory dwelling unit per scope will also include a rear addition (12'-9" x 18'-0") to existing single family dwelling to create new family room.
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | MICHAEL LOPEZ |
| Corrections Issued | 8/14/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 9/13/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 12/22/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 4/1/2021 | MICHAEL LOPEZ |
| Issued | 4/12/2021 | APPLICANT |
| CofO in Progress | 10/28/2024 | GREGG CUMMINGS |
| Permit Finaled | 11/13/2024 | DANIEL ORRANTE |
| CofO Issued | 11/13/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/13/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/15/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/17/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2021 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 6/14/2024 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/3/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/3/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/3/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/3/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/3/2024 | Approved | VINCENT HANLEY |
| Wood Frame | 7/3/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 7/17/2024 | Approved | GREGG CUMMINGS |
| Insulation | 7/17/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 7/22/2024 | Approved | VINCENT HANLEY |
| Sewer | 7/22/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 7/22/2024 | Partial Approval | VINCENT HANLEY |
| Final | 10/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/17/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 10/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/17/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/25/2024 | Approved | GREGG CUMMINGS |
| Final | 10/25/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 10/25/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/25/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 10/25/2024 | Approved | GREGG CUMMINGS |