9462-9464 N ROSLYNDALE AVE 91331

Certificate Information: 9462-9464 N ROSLYNDALE AVE 91331

Application / Permit
20016-10000-16834
Plan Check / Job No.
B20LA12368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Check. Convert existing attached (20' X 17'-11") garage into an accessory dwelling unit per scope will also include a rear addition (12'-9" x 18'-0") to existing single family dwelling to create new family room.
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 MICHAEL LOPEZ
Corrections Issued 8/14/2020 MICHAEL LOPEZ
Quality Review Completed 9/13/2020 PRANITA SHAH
Applicant returned to address corrections 12/22/2020 MICHAEL LOPEZ
Plan Check Approved 4/1/2021 MICHAEL LOPEZ
Issued 4/12/2021 APPLICANT
CofO in Progress 10/28/2024 GREGG CUMMINGS
Permit Finaled 11/13/2024 DANIEL ORRANTE
CofO Issued 11/13/2024 DANIEL ORRANTE
Permit Finaled 11/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/15/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/15/2020 ADRIAN CASTRO
Sewer availability Cleared 12/15/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/17/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2021 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 6/14/2024 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 6/14/2024 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 7/3/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 7/3/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/3/2024 Approved VINCENT HANLEY
HVAC-Rough 7/3/2024 Approved VINCENT HANLEY
PLUMBING-Rough 7/3/2024 Approved VINCENT HANLEY
Wood Frame 7/3/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/17/2024 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval GREGG CUMMINGS
Green Building Rough 7/17/2024 Approved GREGG CUMMINGS
Insulation 7/17/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/17/2024 Partial Approval GREGG CUMMINGS
Drywall Nailing 7/22/2024 Approved VINCENT HANLEY
Sewer 7/22/2024 Approved VINCENT HANLEY
Underground Mechanical 7/22/2024 Partial Approval VINCENT HANLEY
Final 10/17/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 10/17/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Approved GREGG CUMMINGS
Service/Power Release 10/17/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 10/17/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 10/25/2024 Approved GREGG CUMMINGS
Final 10/25/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 10/25/2024 Approved GREGG CUMMINGS
PLUMBING-Final 10/25/2024 Approved GREGG CUMMINGS
Service/Power Release 10/25/2024 Approved GREGG CUMMINGS