15724-15726 W CELTIC ST 91344
Certificate Information: 15724-15726 W CELTIC ST 91344
- Application / Permit
- 20016-10000-16831
- Plan Check / Job No.
- B20LA12365
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Adus. CONVERT EXISTING ATTACHED 20 X 20 GARAGE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | MICHAEL LOPEZ |
| Corrections Issued | 7/30/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 8/7/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 12/14/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 12/31/2020 | MICHAEL LOPEZ |
| Issued | 1/20/2021 | APPLICANT |
| CofO in Progress | 1/13/2022 | MARK JOHNSON |
| Permit Finaled | 3/18/2022 | RONALD MYRICK |
| CofO Issued | 3/18/2022 | RONALD MYRICK |
| Permit Finaled | 3/18/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 10/8/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/8/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2021 | No Access for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 2/3/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 2/3/2021 | Corrections Issued | MARK JOHNSON |
| Sewer | 2/3/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 2/4/2021 | Partial Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 2/24/2021 | Partial Inspection | MARK JOHNSON |
| Green Building Rough | 2/24/2021 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 2/24/2021 | Partial Inspection | MARK JOHNSON |
| MERV13>=Rough | 2/24/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 3/15/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 3/15/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 3/15/2021 | Approved | MARK JOHNSON |
| MERV13>=Rough | 3/15/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 3/15/2021 | Corrections Issued | MARK JOHNSON |
| Wood Frame | 3/15/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 3/19/2021 | Approved | MARK JOHNSON |
| Gas Test | 3/19/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 3/19/2021 | Approved | MARK JOHNSON |
| Insulation | 3/19/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 3/19/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 3/19/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 3/24/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 3/24/2021 | Approved | MARK JOHNSON |
| Final | 5/7/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 5/7/2021 | Approved | MARK JOHNSON |
| MERV13>=Final | 5/7/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 5/7/2021 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 5/7/2021 | Approved | MARK JOHNSON |
| Final | 9/27/2021 | Corrections Issued | MARK JOHNSON |
| Final | 1/12/2022 | OK to Issue CofO | MARK JOHNSON |