5719 N BEVIS AVE 91411
Certificate Information: 5719 N BEVIS AVE 91411
- Application / Permit
- 20016-10000-16784
- Plan Check / Job No.
- B20LA12347
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/28/2020
- Issuing Office
- Current Status
- CofO Issued on 6/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | LAMAR DAVIS |
| Corrections Issued | 8/7/2020 | LAMAR DAVIS |
| Quality Review Completed | 8/17/2020 | TU HUA |
| Applicant returned to address corrections | 9/15/2020 | LAMAR DAVIS |
| Plan Check Approved | 9/18/2020 | LAMAR DAVIS |
| Issued | 9/28/2020 | APPLICANT |
| CofO in Progress | 6/8/2021 | JENNIFER RABUCHIN |
| CofO Issued | 6/19/2021 | MICHAEL SMITH |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/24/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 3129 S HACIENDA BL STE 524 HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/23/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 12/29/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/4/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 2/4/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/4/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/16/2021 | Partial Approval | RONALD COWAN |
| Special/Order Compliance | 2/16/2021 | Partial Approval | RONALD COWAN |
| Wood Frame | 2/16/2021 | Corrections Issued | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 2/22/2021 | Not Ready for Inspection | HENRY KIM |
| Sewer | 2/22/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 3/5/2021 | Corrections Issued | ARAM AVEDISIAN |
| Gas Test | 3/5/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/5/2021 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 3/5/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/15/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 3/15/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 3/15/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 4/6/2021 | Approved | DAVID MATSON |
| Green Building Rough | 4/6/2021 | Approved | DAVID MATSON |
| Insulation | 4/6/2021 | Approved | DAVID MATSON |
| Drywall Nailing | 4/22/2021 | Approved | CHARLES POWELL |
| Final | 5/21/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 5/21/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Not Ready | MARK JOHNSON |
| Smoke Detectors | 5/21/2021 | Approved | MARK JOHNSON |
| Final | 6/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Approved | MICHAEL TEMPLE |
| ELECTRICAL-Final | 6/8/2021 | Approved | JENNIFER RABUCHIN |
| Final | 6/8/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 6/8/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/8/2021 | Approved | JENNIFER RABUCHIN |