2728 S SYCAMORE AVE 90016

Certificate Information: 2728 S SYCAMORE AVE 90016

Application / Permit
20016-10000-16772
Plan Check / Job No.
B20LA12340
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADUs. Convert existing detached garage into accessory dwelling unit per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/10/2021
Issuing Office
Current Status
CofO Issued on 3/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 CRYSTEL MAALOUF
Corrections Issued 7/31/2020 MICHAEL LOPEZ
Quality Review Completed 8/7/2020 PRANITA SHAH
Applicant returned to address corrections 10/20/2020 MICHAEL LOPEZ
Plan Check Approved 2/10/2021 CRYSTEL MAALOUF
Issued 3/10/2021 APPLICANT
CofO in Progress 3/4/2022 JOSE AVILA
CofO Issued 3/24/2022 DEROLD HAUFF
Permit Finaled 3/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/29/2020 RENZ SORIANO
CPC Cleared 9/29/2020 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 9/29/2020 RENZ SORIANO
Sewer availability Cleared 9/29/2020 RENZ SORIANO

Contact Information

Architect , ; Lic. No.: C38436       ,
Contractor Rupert Repairs Inc; Lic. No.: 997462-B 708 N EUCALYPTUS AVE UNIT 102      INGLEWOOD, CA 90302

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2021 Partial Inspection DAVID FEILER
Footing/Foundation/Slab 8/10/2021 Corrections Issued DAVID FEILER
Underground Mechanical 8/10/2021 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 8/23/2021 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 8/23/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/21/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 9/21/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 9/21/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 9/21/2021 Partial Inspection DAVID FEILER
BUILDING-Rough-Frame 9/27/2021 Approved CALEB MEISTER
Deputy Reinf. Concrete 9/27/2021 Conditional Approval CALEB MEISTER
Deputy Wood Construction 9/27/2021 Conditional Approval CALEB MEISTER
ELECTRICAL-Rough 9/27/2021 Conditional Approval CALEB MEISTER
Green Building Rough 9/27/2021 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 9/27/2021 Corrections Issued CALEB MEISTER
PLUMBING-Rough 9/27/2021 Approved CALEB MEISTER
BUILDING-Rough-Frame 10/8/2021 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 10/8/2021 Approved JUSTIN HAWLEY
Green Building Rough 10/8/2021 Approved JUSTIN HAWLEY
HVAC-Rough 10/8/2021 Approved JUSTIN HAWLEY
Insulation 10/8/2021 Partial Approval JUSTIN HAWLEY
Interior/Exterior Lathing 10/8/2021 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Approved LILIANA PORTILLO
Insulation 10/15/2021 Approved LILIANA PORTILLO
Drywall Nailing 10/20/2021 Approved JOSE AVILA
Interior/Exterior Lathing 11/4/2021 Approved LILIANA PORTILLO
Shower Pan 11/4/2021 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/23/2021 Corrections Issued JOSE AVILA
Final 12/23/2021 Corrections Issued JOSE AVILA
Green Building Final 12/23/2021 Corrections Issued JOSE AVILA
HVAC-Final 12/23/2021 Corrections Issued JOSE AVILA
PLUMBING-Final 12/23/2021 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/23/2021 SGSOV Approved JOSE AVILA
Smoke Detectors 12/23/2021 Approved JOSE AVILA
Final 1/12/2022 Corrections Issued JOSE AVILA
Green Building Final 1/12/2022 Approved JOSE AVILA
Final 3/4/2022 OK to Issue CofO JOSE AVILA