2728 S SYCAMORE AVE 90016
Certificate Information: 2728 S SYCAMORE AVE 90016
- Application / Permit
- 20016-10000-16772
- Plan Check / Job No.
- B20LA12340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADUs. Convert existing detached garage into accessory dwelling unit per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 7/31/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 8/7/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 10/20/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 2/10/2021 | CRYSTEL MAALOUF |
| Issued | 3/10/2021 | APPLICANT |
| CofO in Progress | 3/4/2022 | JOSE AVILA |
| CofO Issued | 3/24/2022 | DEROLD HAUFF |
| Permit Finaled | 3/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2020 | RENZ SORIANO |
| CPC | Cleared | 9/29/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 9/29/2020 | RENZ SORIANO |
Contact Information
| Architect | , ; Lic. No.: C38436 | , |
| Contractor | Rupert Repairs Inc; Lic. No.: 997462-B | 708 N EUCALYPTUS AVE UNIT 102 INGLEWOOD, CA 90302 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2021 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 8/10/2021 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 8/10/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 8/23/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 8/23/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/21/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 9/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 9/21/2021 | Partial Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/27/2021 | Approved | CALEB MEISTER |
| Deputy Reinf. Concrete | 9/27/2021 | Conditional Approval | CALEB MEISTER |
| Deputy Wood Construction | 9/27/2021 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 9/27/2021 | Conditional Approval | CALEB MEISTER |
| Green Building Rough | 9/27/2021 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 9/27/2021 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 9/27/2021 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/8/2021 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/8/2021 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 10/8/2021 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 10/8/2021 | Approved | JUSTIN HAWLEY |
| Insulation | 10/8/2021 | Partial Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/8/2021 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Approved | LILIANA PORTILLO |
| Insulation | 10/15/2021 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/20/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/4/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 11/4/2021 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/23/2021 | Corrections Issued | JOSE AVILA |
| Final | 12/23/2021 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/23/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/23/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/23/2021 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/23/2021 | Approved | JOSE AVILA |
| Final | 1/12/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/12/2022 | Approved | JOSE AVILA |
| Final | 3/4/2022 | OK to Issue CofO | JOSE AVILA |